Availability / Reliability / RAP / Markov modelling / SMO / PSO / Manufacturing System

Аннотация научной статьи по медицинским технологиям, автор научной работы — Sarita Devi, Nakul Vashishth, Deepika Garg

In today’s scenario manufacturing industries are highly complex and prone to failure. That’s why redundancy allocation problem (RAP) and time dependent availability analysis plays a major role for the successful life cycle of a manufacturing industry. RAP is a Np-hard problem which is very difficult to solve by traditional methods. Therefore in this paper, RAP for the Manufacturing system is solved by Spider monkey optimization. SMO is recent meta-heuristic technique. Till now it is not used to solve RAP. Further results are compared with the Particle swarm optimization algorithm and comparison validates the better performance of SMO in this problem. As mentioned above, for avoiding the complete breakdown of the manufacturing system time-dependent availability is analyzed in this study. Firstly failure and repair data is collected from the manufacturing system then with the help of this information transition diagram is developed. Further equations are developed from transition diagram by using Markov birth death process then equations are solved with the use of Runge-Kutta method. This methodology is implemented in MATLAB.

i Надоели баннеры? Вы всегда можете отключить рекламу.
iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.
i Надоели баннеры? Вы всегда можете отключить рекламу.

Текст научной работы на тему «RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING SYSTEM: SMO AND PSO»

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING SYSTEM: SMO AND PSO

Sarita Devi1, Nakul Vashishth2, Deepika Garg3,*

1,2,3 GD Goenka University, Gurugram, Haryana [email protected], [email protected] Corresponding author: *[email protected]

Abstract

In today's scenario manufacturing industries are highly complex and prone to failure. That's why redundancy allocation problem (RAP) and time dependent availability analysis plays a major role for the successful life cycle of a manufacturing industry. RAP is a Np-hard problem which is very difficult to solve by traditional methods. Therefore in this paper, RAP for the Manufacturing system is solved by Spider monkey optimization. SMO is recent meta-heuristic technique. Till now it is not used to solve RAP. Further results are compared with the Particle swarm optimization algorithm and comparison validates the better performance of SMO in this problem. As mentioned above, for avoiding the complete breakdown of the manufacturing system time- dependent availability is analyzed in this study. Firstly failure and repair data is collected from the manufacturing system then with the help of this information transition diagram is developed. Further equations are developed from transition diagram by using Markov birth death process then equations are solved with the use of Runge-Kutta method. This methodology is implemented in MATLAB.

Keywords: Availability, Reliability, RAP, Markov modelling, SMO, PSO, Manufacturing System.

1. Introduction

The demand for high-quality products and system reliability is increasing day by day in the current world business competitive market. It is observed that only those products will stand in the market, which is up to the desired market level and consumer's satisfaction level. Along with the increasing demand of quality products/systems in practical engineering the importance of reliability optimization is also increased. With the limitation of constraints (costs/ weight), important measurements can be used to increase system reliability. There are several measurements which can be used for increasing the system reliability but redundancy allocation is the important strategy for improving the reliability of the system with constraints. Redundancy allocation problem is a reliability optimization problem. It involves selection of components with appropriate levels of redundancy or reliability to maximize the system reliability under the defined constraints. The redundancy allocation problem was solved by heuristic algorithm(HA) and constraint optimization algorithm (COGA) [1].

In this study, RAP of the manufacturing system is solved by PSO and SMO techniques. A few years back, PSO technique which was a peculiarity has now become the zest of researchers in the world. PSO is a nature-inspired and population-based stochastic technique. It was first introduced in the year 1995 [2]. PSO was applied for solving RAP due to its robustness and its simplicity [3]. Hybrid PSO with local search algorithm was applied for solving RAP [4]. Comparative analysis is also done with Tabu search and Multi weighted objectives solutions. A hybrid PSO algorithm with

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76) SYSTEM: SMO AND PSO_Volume 18, December 2023

local search was proposed for solving RAP in series-parallel system [5]. The reformulate of a crisp

optimization problem from FMOOP has been done and then applied PSO for solving fuzzified

MOOP under a number of constraints [6]. A hybrid particle swarm optimization with constraint

optimization genetic algorithm was proposed for solving a RAP [7]. A bare bones PSO and

sensitivity based clustering was proposed for solving multi-objective RAP [8]. Multi-objective PSO

(MOPSO) was applied for solving RAP in an interval environment [9]. The effectiveness of the

algorithm is demonstrated by two numerical examples in their study.

An improved PSO was applied for solving RAP [10]. Inertia and acceleration coefficients of the classical PSO are improved by considering normal distribution for the coefficients which improved the results. The formulation of RAP with global reliability (g-reliability) has been done and applied improved PSO algorithm with a specific particles under RAP [11]. The optimization of the reliability of the system was done with the allocation of the redundancy of the manufacturing systems using hybrid genetic and particle swarm algorithm [12]. The redundancy allocation problem was solved by using hybrid genetic simulating annealing algorithm and a comparative study is presented in this research [13]. The reliability of the pharmaceutical plant was optimized by using heuristic algorithm [14].

SMO algorithm is introduced by J.C. Bansal in the year 2014 [15]. SMO is stimulated by social behavior of a special kind of monkeys called as spider monkeys. Spider monkeys have been classified as animals with fission-fusion social structure. These monkeys follow fission-fusion social systems as they initially work in a large group and but as their needs change over time, they split into smaller forage groups, each led by an adult female. Consequently, the suggested approach can be roughly categorized as drawing inspiration from the intelligent foraging behavior of spider monkeys with fission-fusion social structures. The initialize phase, the global leader phase (GLP), the local leader phase (LLP), and the decision phase are the main four phases of the SMO algorithm.

SMO was used as an optimization technique for the community of electromagnetic [16]. SMO was enforced to figure out the optimal PIDA controller parameters to control the induction motor [17]. This was the initial strategy to attain such a goal using SMO. The outcomes were compared to the Dorf and PSO technique, and it was noticed that SMO outperformed both of other methods.

An effort was made to solve confined consistent optimization problem by employing the SMO algorithm for restricted optimization problems [18]. A new search feature was developed in SMO called Power Law-based Local Search (PLLS) [19]. The SMO technique was applied to classify diabetes and developed SMO that may be used to design the SM-Rule-Miner, an effective rule miner for diabetes diagnosis [20]. Comparing SM-Rule-Miner to other meta-heuristic based rule mining techniques, it was found that it had the second-best average classification performance rating and the highest accuracy sensitivity rating.

A survey was conducted on SMO, its applications, and variants, and compared the findings to other algorithms [21]. Recently, a modern Discrete Spider Monkey Optimization (DSMO) technique was applied to solve the problem of travelling salesmen [22]. SMO and deep neural networks were applied for the future forecasting of brands for marketing purposes by using Twitter data [23]. Further investigation showed that SMO was more reliable and computationally efficient than other techniques.

Most of the products are manufactured in manufacturing plants, which consist of several subsystems performing different operations. These subsystems are made up of mechanical parts that may fail due to wear and tear and also due to usage with the passage of time. The failure is a random aspect that is always related to the operative condition of any physical system. Its causes are either deterioration in the components of the system and human errors.

As a result, the primary priority is to maintain system performance measures such as reliability and availability and redundancy in order to achieve high-profit targets and productivity in terms of system failures. Reliability optimization and availability are closely related concepts. Reliability

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76)

SYSTEM: SMO AND PSO_Volume 18, December 2023

optimization involves improving the system's ability to operate without failure, while availability is a measure of the system's ability to be operational when it is required.

The behavior analysis of time-dependent availability of the manufacturing system is measured using the Runge-Kutta fourth-order method in MATLAB. The area synthesis procedure's availability was considered for the compost industry [24]. The reliability and quality attributes for two stochastic models of a framework were discussed which have two non-indistinguishable components, arranged in series, each unit having cold standby of same/equal capacity [25]. The time-dependent availability of repairable m-out of -n and cold standby systems were investigated using arbitrary distributions and repair facilities [26]. An instructional study on reasonable strategies for Markov modeling was considered [27]. The analysis of availability formulations of standby frameworks of parallel units was done [28].

The study of a two-unit warm reserve framework was discussed that expects a bivariate exponential thickness for the joint circulation of sub-units failure/repair rates [29]. The number of operational stages of a repairable Markov framework during interim finite time was studied [30]. Finite Markov processes were utilized to model a repairable framework with time-independent transition rates concerning individual conditions in reliability analysis. The complex system with the imperfect switching using various techniques such as the Markov-method and supplementary variable method was considered [31]. Failure/repair rates are considered as constant. Further, the N sub-unit framework was analyzed in which M sub-unit are warm standby and R sub units are used to repair the failed sub-units [32]. A closed equation is developed to discover reliability parameters under certain constraints and conclusion is made on the basis of this study that without a repairman, framework reliability diminishes. The shortest path study in stochastic systems; acquainted another methodology and getting the reliability capacity of time-subordinate frameworks with standby mode was discussed [33]. The application of pod propulsion that the number of vessel types has been increased consistently over the last two decades was highlighted [34]. A model was developed using Markov process [35]. Regression analysis was utilized in that study to gauge the different transition rates of the model. A cattle feed plant consisting of seven subsystems arrange in series was analyzed by using matrix method [36]. The mathematical model has been developed using the Markov birth-death process and made a transition diagram. The system's behavior was analyzed over an implanted Markov chain method [37]. The discrete-time and continuous-time measures were provided for each of the explicit Markov and two semi-Markov models for thermal availability plant using simulation modeling [38]. The performance of the steam-generating system was evaluated and analyzed for the availability of a thermal plant [39]. In their study, the system consists three subunits with a high-pressure heater, boiler drum, and economizer associated in series, parallel, and combination of these. Further, Markov model was used for analyzing the reliability of coal crushing unit of Badarpur thermal power plant [40]. Transition diagram and differential equations are developed and solved by a recursive approach. Markov modeling was used for the fertilizer plant and analyzed the reliability of the system [41]. Their study deals with Markov birth-death procedure, and the failure rates and repair rates of every system. The RPGT technique was used for the behavioral study of two units [42].

A stochastic model was analyzed that was to be considered two-unit redundant framework [43]. In this framework, the operational unit's software and hardware elements on failure are substituted by the cold standby unit, and replacement may be possible on fractional failure also. Markov model was used to analyze the reliability of the phased-mission system (PMS) [44]. Mathematical modeling is done by utilizing the state merging method. The analyze the reliability of the manufacturing system is done by Fault tree analysis [45].

2. Problem Description and Formulation

The following assumptions and notations are taken for solving RAP and to draw a transition diagram depicting the various possible working, reduced, and failed states, together with the transitional failure and repair rates of subsystems to analyze and discuss the behavior of time-dependent availability of the manufacturing system.

2.1. Assumptions

The assumptions are follows:

• Failure and repair rates are considered constant and statistically independent of each other. Not more than one unit can fail at a time.

• The repaired units work as if a new one.

• There is only one subsystem which has units in parallel; hence it can work in a reduced capacity, on the failure of all units of this subsystem, there is the complete failure of the system.

• All other subsystems (except one given above) have subunits in series, so if a single unit of these subsystems fail, then the whole of the system fails completely.

• No unit fails further when the system is reached in failed state.

2.2. Notations

The notations used in this research work are as follows:

Rs(n): g(.):

ni:

h (n): n:

Rs:

y*:

System reliability

A function that yields the system reliability, based on unique subsystems, and which depends on the configuration of the subsystems

number of ith subsystems Cost of ith subsystem number of subsystems Rupees

(n1,n2, n3,..., n7) is optimal solution

A, B, C, D, E, F, G: Indicate that the subsystems are working in full capacity.

B: Indicate the reduced state of the subsystem B.

Ai (i=l, 2, 3, ..., 7, 8): Failure rates of the subsystems A, B, C, D, ..., G, Brespectively.

(i=1, 2, 3, ..., 7, 8): Repair rates of the subsystems a, B, c, d, ..., g, brespectively.

a, b, c, d, e, f, g Indicate the failure state of the subsystems A, B, C, D, E, F, G

Pi (t) (i=0,1, 2, 3, ..., 14) probability that system is in the ith state.

I I Failed state

0 Full working state

1 I Reduced state

50 ABCDEFG

52 ABCDEFG

51 aBCDEFG

53 ABcDEFG

54 ABCdEFG

55 ABCDeFG

56 ABCDEfG

57 ABCDEFg

58 aB CDEFG

59 AbCDEFG S10 AB cDEFG

SYSTEM: SMO AND PSO_Volume 18, December 2023

511 ASCdEFG

512 AB CDeFG

513 AB CDEfG

514 AS CDEFg

2.3. System Description The system is described as:

• Data is collected from the manufacturing system.

• Data related to subsystems (machines) and the number of units connected in that subsystem, regarding subsystems, their configuring, and working.

• The system consists of seven subsystems: Overhead Crane, Roller, Blanking Machine, Stacker machine, Press machine, Molding, and Packing. These subsystems are connected in series for the proper functioning of the system at full capacity initially.

• Overhead Crane Subsystem (A): There is only one overhead crane having subunits in series.

• Roller Subsystem (B): The roller consists of one unit having subunits in parallel. It rolls the steel roll connected to the blanking machine.

• Blanking Machine (C): The blanking machine cuts the blanks having subunits in series.

• Stacker Subsystem (D): Blanks are stacked with the help of a stacker having subunits in series.

• Press Subsystem (E): Blanks are pressed for the desired shape by the Press subsystem having subunits in series.

• Molding Machine (F): The molding machine molds the pressed blanks for the desired shape having subunits in series.

• Packing Subsystem (G): Packing machine packs the final product having subunits in series.

Structural Representation of the system

Figure 1: System Structure

Problem Statement

In this study, the data related to the subsystem's reliability and cost are presented in Table 1 of the manufacturing system. The given cost constraint is C= Rs 30490000. The objective function for the manufacturing system is to maximize the reliability and subject to cost constraint. The problem is represented by Equation (2), and the cost constraint presented by Equation (3). The problem is to maximize :

Rs(n) = g (Ri(ni), ...., Rn(nn)) = nLiRi O) (1)

Ri(ni) = ni1[i-mni)r] (2)

YJ=1 h(ni) * ni < 30490000 (3)

Table 1: Reliability and Cost

Subsystem ni n2 n3 n4 ns n6 n7

Reliability of subsystem Ri(nO 0.99 0.9762 0.9188 0.8155 0.8655 0.9287 0.9453

Cost of subsystem(Rs) h(ni) 1280000 960000 2500000 1050000 10500000 950000 250000

Optimization using PSO and SMO Algorithms

Inspired by swarm intelligence in nature, PSO was developed by Kennedy and Eberhart in 1995

[2].

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

PSO is motivated by the social behavior of bird flocking and applies this behavior to guide the particles for searching the global optimal solutions. Mostly, in PSO, the particle population are randomly spread throughout the search space. The particles are considered to be flying in the search space. PSO searches for optima by updating generations after being initialized with a collection of random particles (solutions).

Each particle is modified by the following the two best values in every iteration. The first one is the best solution (fitness) it has obtained so far. This value is known as pbest. Another "best" value that is obtained by the particle swarm optimizer is the best value obtained so far by any particle in the population. This global best value is known as gbest. When a particle takes part of the population as its topological neighbors, the best value is a local best and is called lbest. The position and velocity updated with the help of two equations:

V = wvt + C1r1(pbest,i - yi) + C2r2(gbest - y{) Ji=Ji + V

(4)

(5)

Results of PSO

The results of the redundancy allocation solved by PSO are represented in tabular form. Table 2 shows different redundant units for various subsystems obtained by using PSO.

Table 2: Results of PSO for the Manufacturing System

Subsystems ni n2 n3 n4 n5 n6 n7

Redundancy 2 1 2 3 1 3 3

of the

subsystems

SMO is stimulated by social behavior of a special kind of monkeys called as spider monkeys. Spider monkeys have been classified as animals with fission-fusion social structure. These monkeys follow fission-fusion social systems as they initially work in a large group and but as their needs change over time, they split into smaller forage groups, each led by an adult female. Consequently, the suggested approach can be roughly categorized as drawing inspiration from the intelligent foraging behavior of spider monkeys with fission-fusion social structures. The initialize phase, the global leader phase (GLP), the local leader phase (LLP), and the decision phase are the main four phases of the SMO algorithm.

Results of SMO

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76) SYSTEM: SMO AND PSO_Volume 18, December 2023

The results of RAP of the manufacturing system obtained by SMO are also represented in

tabular form. Optimum redundant units of each subsystems redundant of each subsystem are

represented in Table 3.

Table 3: Results of SMO for the Manufacturing System

Subsystems m n2 n3 n4 n5 n6 n7

Redundancy of 3 the subsystems 2 3 3 1 2 5

Comparative analysis of the results of RAP by PSO and SMO

The comparative analysis of the results obtained by two algorithms PSO and SMO for the Manufacturing system in this research.

The comparative analysis of the results of RAP using PSO and SMO are represented in Table 3. Obtained results demonstrate the increase in the reliability of the manufacturing system.

Table 4: Comparison of the best optimal solution by PSO and SMO

Subsystems ni n2 n3 n4 n5 n6 n7 Increase in the reliability

Redundancy

PSO 2 3 2 5 1 3 5

SMO 3 2 3 5 2 2 5

The comparative analysis of the results obtained by these algorithms are described as follows:

The reliability value of the system before applying these two algorithms is 0.5236.

The values of the redundant units of each subsystem before using these algorithms are

n*=(1,1,1,1,1,1,1).

The optimal solution of RAP using PSO is Rs(n*) = 0.8332 and the redundancy units n* = (2, 1, 2, 3, 1, 3, 3).

The increment in the value of reliability can be 51%.

The final solution of RAP using SMO is Rs(n*) = 0.8504 and redundant units of each subsystem n*= (3, 2, 3, 3, 1, 2, 4).

The reliability value of the system can be increased by 55% using SMO. The reliability value of the system is increased by using both the algorithms.

The redundancy units of the subsystems n* are distinct for every subsystem by both the algorithms used in this research.

The larger increment in the reliability value of the system using SMO which is 55%.

The results shows that the batter results obtained by SMO and reliability is also improved by SMO

than PSO.

Time dependent availability

The state transition diagram of the manufacturing system is drawn as follows:

2.4. State Transition Diagram

The first order Markov-process is used to develop the state transition diagram. A state transition diagram, together with transition rates, is drawn to describe the various states of the system, is given below in Figure 1.

Figure 2: State Transition Diagram of Manufacturing System

2.5. Methodology- Runge-Kutta Fourth Order

Differential equations associated with the system are written using the Markov birth-death method, which is further solved using Runge-Kutta fourth-order method by ODE- 45 in MATLAB. Table and graph are drawn to represent the results of the time-dependent availability of the manufacturing system.

Mathematical Modelling:

The differential equations governing the system using the Markov birth-death process are as follows:

P'(t) + + X2 + A3 + A4 + + A6 + A7)P0(t) = ViPi(t) + ^(O + ^Ps(t) + ^(t) + V5P5(t) +

^6P6(t) + +^7P7(t) (6)

^1P1(t) = A1P0(t) (7)

P2(t) + (Ai +^2+A3+A4 + A5+A6+A7+ Ae)P2(t) = A2P0(t) + hPe(t) + ^eP9(t) + ^sPio(t) +

^Pii(t) + V5Pi2(t) + VePis(t) + lbPi4(t) (8)

ß3P3(t) = A3P0(t) (9)

ß4P4(t) = A4P0(t) (10)

ß5P5(t) = A5P0(t) (11)

ß6P6(t) = A6P0(t) (12)

ß7P7(t) = A7P0(t) (13)

ß1P8(t) = A^t) (14)

ß8P9(t) = ^(0 (15)

ß3Pio(t) = hP2(t) (16)

ß4Pu(t) = A4P2(t) (17)

ß5P!2(t) = A5P2(t) (18)

ßeP^t) = A6P2(t) (19)

V7Pi4(t) = A7P2(t) (20)

3. Results

The results of time-dependent availability obtained using the Runge-Kutta fourth-order method by ODE 45 in MATLAB are represented below in Table 5 and Figure 2.

Table 5: Time-dependent availability

Time Availability

0 1

20 0.827

40 0.8203

60 0.7932

80 0.7757

100 0.7644

120 0.7561

140 0.7515

160 0.7451

180 0.7328

200 0.7215

The availability of the system is also determined after the reliability of the system is improved by the technique SMO.

Figure 3: Time-Dependent Availability

4. Conclusion

In this study, redundancy is used as a key strategy for reliability optimization to improve system performance, minimize failures, and enhance the overall reliability and availability of a system or process. RAP is a mathematical optimization problem that involves determining the

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76) SYSTEM: SMO AND PSO_Volume 18, December 2023

optimal allocation of redundancy to subsystems in order to improve the system reliability and

availability. RAP is solved by SMO and results are compared with PSO.

RAP of the manufacturing system is solved by two optimization techniques PSO and SMO. The reliability of the manufacturing system is improved by both the techniques. But the increment of 55% in reliability of the manufacturing system by SMO which is greater than 51% by PSO.

The availability of the manufacturing system is also analyzed using Markov modelling. The calculations are done using Runge-Kutta method of forth order in MATLAB using the tool ode 45. It is concluded that system availability is a decreasing function of time. As time increases, the availability value of the system decreases.

5. Author Contribution Statement

In this manuscript all authors "contributed equally" to the study.

References

[1] Devi, S., Garg, D. (2017), "Redundancy-allocation in Neel Metal Products Limited", Indian Journal of Science and Technology ,10(30): 1-5.

[2] Kennedy, J., Eberhart, R. (1995). Particle swarm optimization. In Proceedings of ICNN'95-international conference on neural networks, IEEE, 4: 1942-1948.

[3] Poli, R., Kennedy, J., & Blackwell, T. (2007). Particle swarm optimization: An overview. Swarm intelligence, 1, 33-57.

[4] Beji, N., Jarboui, B., Eddaly, M., & Chabchoub, H. (2010). A hybrid particle swarm optimization algorithm for the redundancy allocation problem. Journal of Computational Science, 1(3), 159-167.

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

[5] Wang, Y., Li, L. (2012). Heterogeneous redundancy allocation for series-parallel multi-state systems using hybrid particle swarm optimization and local search. IEEE Transactions on Systems, Man, and Cybernetics - Part A: Systems and Humans, 42(2): 464-474.

[6] Garg, H., Sharma, S. P. (2013). Multi-objective reliability-redundancy allocation problem using particle swarm optimization. Computers & Industrial Engineering, 64(1), 247-255.

[7] Devi, S., Sahu, A., Garg, D. (2017), "Redundancy optimization problem via comparative analysis of H-PSOCOGA", IEEE Explore, 18-23.

[8] Zhang, E., Wu, Y., & Chen, Q. (2014). A practical approach for solving multi-objective reliability redundancy allocation problems using extended bare-bones particle swarm optimization. Reliability Engineering & System Safety, 127, 65-76.

[9] Zhang, E., & Chen, Q. (2016). Multi-objective reliability redundancy allocation in an interval environment using particle swarm optimization. Reliability Engineering & System Safety, 145, 83-92.

[10] Marouani, H. (2021). Optimization for the redundancy allocation problem of reliability using an improved particle swarm optimization algorithm. Journal of Optimization, 2021, 1-9.

[11] Li, S., Chi, X., & Yu, B. (2022). An improved particle swarm optimization algorithm for the reliability-redundancy allocation problem with global reliability. Reliability Engineering & System Safety, 225.

[12] Devi, S., Garg, D. (2020). Hybrid genetic and particle swarm algorithm: redundancy allocation problem. International Journal of System Assurance and Engineering Management, 11(6): 313319.

[13] Garg, D., Devi, S. (2021). RAP via hybrid genetic simulating annealing algorithm. International Journal of System Assurance and Engeering Management, Springer.

[14] Dahiya, T., Garg, D., Devi, S., Kumar, R. (2021). Reliability optimization using heuristic algorithm in pharmaceutical plant. Reliability: Theory & Applications, 16(3): 195-205.

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76) SYSTEM: SMO AND PSO_Volume 18, December 2023

[15] Bansal, J. C., Sharma, H., Jadon, S. S., & Clerc, M. (2014). Spider monkey optimization algorithm for numerical optimization. Memetic computing, 6, 31-47.

[16] Al-Azza, A. A., Al-Jodah, A. A., & Harackiewicz, F. J. (2016). Spider monkey optimization: A novel technique for antenna optimization. IEEE Antennas and Wireless Propagation Letters, 15, 10161019.

[17] Sharma, A., Sharma, H., Bhargava, A., & Sharma, N. (2016). Optimal design of PIDA controller for induction motor using spider monkey optimization algorithm. International Journal of Metaheuristics, 5(3-4), 278-290.

[18] Gupta, K., Deep, K., Bansal, J.C. (2017). Spider monkey optimization algorithm for constrained optimization problems. Soft Comput. Springer Berlin Heidelberg, 21: 6933-62.

[19] Sharma, A., Sharma, H., Bhargava, A., & Sharma, N. (2017). Power law-based local search in spider monkey optimisation for lower order system modelling. International Journal of Systems Science, 48(1), 150-160.

[20] Cheruku, R., Edla, D. R., & Kuppili, V. (2017). SM-Rule Miner: Spider monkey based rule miner using novel fitness function for diabetes classification. Computers in biology and medicine, 81: 79-92.

[21] Agrawal, V., Rastogi, R., & Tiwari, D. C. (2018). Spider monkey optimization: a survey. International Journal of System Assurance Engineering and Management, 9: 929-941.

[22] Akhand, M. A. H., Ayon, S. I., Shahriyar, S. A., Siddique, N., & Adeli, H. (2020). Discrete spider monkey optimization for travelling salesman problem. Applied Soft Computing, 86.

[23] Kothamasu, L. A., & Kannan, E. (2022). Sentiment analysis on twitter data based on spider monkey optimization and deep learning for future prediction of the brands. Concurrency and Computation: Practice and Experience, 34(21), e7104.

[24] Singh, J., Pandey, P.C., and Kumar, D. (1990). Designing for reliable operation of urea synthesis in the fertilizer industry. Microelectronics Reliability, 30 (6): 1021 - 1024.

[25] Moafib, S. E., Goel, L. R., and Gupta, R. (1991). Comparison of two stochastic models for two-unit series system with cold standbys. Microelectronic Reliability, 31 (6): 1105 - 1111.

[26] Gurov, S. V., Utkin, L.V. (1995), "A new method to compute reliability of repairable series systems by arbitrary distributions". Microelectronics Reliability, 35 (1): 81-85.

[27] Kitchin, J. K. (1988). Practical Markov modelling for reliability analysis. In Proceedings of the Annual Reliability and Maintainability Symposium, 290 -296.

[28] Aven, T. (1990). Availability formulae for standby systems of similar units that are preventively maintained. IEEE Transactions on Reliability, 39 (5): 603 - 606.

[27] Goel, L. R., and Shrivastava, P. A.(1992). Warm standby redundant system with correlated failures and repairs. Microelectron Reliability, 32 (6): 793 -797.

[28] Csenki, A. (1994), "Joint availability of systems modelled by finite semi-Markov processes". Applied Stochastic Models and Data Analysis, 10(4): 279-293.

[29] Goel, P.(1997). Availability Analysis and Cost Optimization of Complex System having Imperfect Switch. Ph.D. Thesis, Kurukshetra, India.

[30] Arulmozhi, G.(2002). Reliability of M-out of N Warm Standby System with R Repair Facilities. Operational Research Society of India, 39 (2): 77 - 88.

[31] Azaron, A., Katagiri, H., Sakawa, M., and Modarres, M.(2005). Reliability function of a class of time dependent systems with standby redundancy. European Journal of Operational Research, 16 (4): 378 - 386.

[32] Aksu, S., and Turan, O.(2006). Reliability and availability of Pod propulsion system. Journal of Reliability Engineering International, 22: 41 - 58.

[33] Mishari, S.T., Suliman, S. (2008), "Integrating Six-sigma with other reliability improvement methods in equipment reliability and maintenance applications. Journal of Quality in Maintenance Engineering, 14(1): 59-70.

[34] Garg, D., Kumar, K., and Singh, J. (2009). Availability analysis of a cattle feed plant using matrix method. International Journals of engineering, 3 (2): 127 - 133.

Sarita Devi, Nakul Vashishth and Deepika Garg

RAP AND AVAILABILITY ANALYSIS OF MANUFACTURING RT&A, No 4 (76) SYSTEM: SMO AND PSO_Volume 18, December 2023

[35] Umemura, T. and Dohi, T. (2010). Availability Analysis of an Intrusion Tolerant Distributed Server System with Preventive Maintenance. IEEE Transactions on Reliability, 59 (1): 18 - 29.

[36] Gupta, S., and Tewari, P. C.(2011). Simulation modeling in an availability thermal power plant. Journal of engineering science and Technology review, 4(2): 110 - 117.

[37] Kumar, R., Sharma, A. K., and Tewari, P. C.(2012). Markov approach to evaluate the availability simulation model for power generation system in athermal power plant. nternational Journal of Industrial Engineering Computations, 3 (5): 743 - 750.

[38] Kumar, J., Kadyan, M. S. and Malik, S. C.(2013). Profit Analysis of a 2 out of 2 Redundant System with Single Standby and Degradation of the Units after Repair. International Journal of System Assurance Engineering and Management, 424 -434.

[39] Aggarwal, A., Kumar, S., and Singh, V.(2015). Markov modeling and reliability analysis of urea synthesis system of a fertilizer plant. Journal of industrial engineering international, 11: 1-14.

[40] Goyal, V., Goel, R., and Goel, P.(2015). Behavioral Analysis of Two Unit System with Preventive Maintenance in Both Units and Degradation in One Unit. International Journal of Engineering Technology Management and Applied Sciences, 3: 190 - 197.

[41] Kumar, A., Garg, D., and Goel, P. (2017). Mathematical modelling and profit analysis of an edible oil refinery industry. Airo International Research Journal, 12: 1 - 8..

[44] Hua, Y., Li., G., Lie, Q., and Ping, W.(2018). Simplified Markov Model for Reliability Analysis of Phased-Mission System Using States Merging Method. J. Shanghai Jiao Tong Univ. (Sci.), 23 (3): 418 - 422.

[45] Devi, S., Garg, D. (2019), "Reliability Analysis of Manufacturing Plant Via Fault Tree Analysis", Journal of Advances and Scholarly Researches in Allied Education, 16(5): 256-259.

i Надоели баннеры? Вы всегда можете отключить рекламу.