Incentive systems in project management Текст научной статьи по специальности «Экономика и бизнес»

CC BY
221
38
i Надоели баннеры? Вы всегда можете отключить рекламу.
Ключевые слова
PROJECT / TEAM / CUMULATIVE UNIFIED INCENTIVE SYSTEMS / GROUP INCENTIVE SCHEMES / ПРОЕКТ / КОМАНДА / ОБЪЕДИНЕННЫЕ УНИФИЦИРОВАННЫЕ СИСТЕМЫ СТИМУЛИРОВАНИЯ / ГРУППОВЫЕ СИСТЕМЫ СТИМУЛИРОВАНИЯ

Аннотация научной статьи по экономике и бизнесу, автор научной работы — Barkalov S.A., Burkov V.N., Kalinina N.Yu., Nasonova T.V.

Analysis of the current state of project management shows a significant increase in the number of projects implemented in the spheres of construction, public administration, energy, consulting, and digital technologies. Professional project management allows to effectively allocate responsibilities and responsibilities between project participants, save money and time, reduce risks. Understanding the importance of future development, the heads of organizations are increasingly using project management methods to create competitive advantages, and in the applied theory of management of organizational systems, more attention is paid to the teamwork of the organization's personnel. An important task in the management of the project team is the formation of a system of incentives for its participants, whose task is to ensure the implementation of the project on time without additional budget expenditures. In order to maintain the motivation of project team members, individual and unified incentive schemes. The disadvantage of individual incentive systems is, firstly, unequal conditions for encouraging different groups of performers, and secondly, the danger of manipulation, that is, deliberate distortion of information on the amount of work and costs transferred from the members of the project team. In order to exclude distortion of information and reduce tension in the project team, unified incentive schemes apply when the incentive mechanism is the same for all performers. Intermediate position is occupied by the group incentive schemes, when a number of project operations are divided into groups, for executors of each of which a unified incentive system is applied. The article considers jumping unified stimulation systems, and the problem of choosing the optimal group incentive system is solved.

i Надоели баннеры? Вы всегда можете отключить рекламу.
iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.
i Надоели баннеры? Вы всегда можете отключить рекламу.

СИСТЕМЫ СТИМУЛИРОВАНИЯ В УПРАВЛЕНИИ ПРОЕКТАМИ

Анализ современного состояния управления проектами показывает существенное увеличение количества проектов, реализуемых в сферах строительства, государственного управления, энергетики, цифровых технологий. Понимая важность будущего развития, руководители организаций применяют методы управления проектами для создания конкурентных преимуществ, а в прикладной теории управления организационными системами все большее внимание уделяется командной деятельности персонала организации. Важная задача в управлении проектной командой формирование системы стимулирования ее участников, задача которой обеспечить выполнение проекта в срок без дополнительных расходов бюджета. В целях поддержания мотивации участников проектных команд применяются индивидуальные и унифицированные системы стимулирования. Недостатком индивидуальных систем стимулирования является, во-первых, неравные условия поощрения различных групп исполнителей, а во-вторых, опасность манипулирования, то есть сознательного искажения информации об объемах работ и затратах, передаваемой от членов проектной команды. Для того чтобы исключить искажение информации и снизить напряженность в команде проекта, применяют унифицированные системы стимулирования, когда механизм стимулирования один и тот же для всех исполнителей. Промежуточное положение занимают групповые системы стимулирования, когда множество операций проекта разбивается на группы, для исполнителей каждой из которых применяется унифицированная система стимулирования. В статье рассматриваются скачкообразные унифицированные системы стимулирования, и решается задача выбора оптимальной групповой системы стимулирования.

Текст научной работы на тему «Incentive systems in project management»

DOI: 10.14529/ctcr180415

INCENTIVE SYSTEMS IN PROJECT MANAGEMENT

S.A. Barkalov1, barkalov@vgasu.vrn.ru, V.N. Burkov2, vlab17@bk.ru, N.Yu. Kalinina1, kalinina@vgasu.vrn.ru, T.V. Nasonova1, tnasonova@vgasu.vrn.ru

1 Voronezh State Technical University, Voronezh, Russian Federation,

2 V.A. Trapeznikov Institute of Control Sciences of Russian Academy of Sciences, Moscow, Russian Federation

Analysis of the current state of project management shows a significant increase in the number of projects implemented in the spheres of construction, public administration, energy, consulting, and digital technologies. Professional project management allows to effectively allocate responsibilities and responsibilities between project participants, save money and time, reduce risks. Understanding the importance of future development, the heads of organizations are increasingly using project management methods to create competitive advantages, and in the applied theory of management of organizational systems, more attention is paid to the teamwork of the organization's personnel.

An important task in the management of the project team is the formation of a system of incentives for its participants, whose task is to ensure the implementation of the project on time without additional budget expenditures. In order to maintain the motivation of project team members, individual and unified incentive schemes.

The disadvantage of individual incentive systems is, firstly, unequal conditions for encouraging different groups of performers, and secondly, the danger of manipulation, that is, deliberate distortion of information on the amount of work and costs transferred from the members of the project team. In order to exclude distortion of information and reduce tension in the project team, unified incentive schemes apply when the incentive mechanism is the same for all performers. Intermediate position is occupied by the group incentive schemes, when a number of project operations are divided into groups, for executors of each of which a unified incentive system is applied.

The article considers jumping unified stimulation systems, and the problem of choosing the optimal group incentive system is solved.

Keywords: project, team, cumulative unified incentive systems, group incentive schemes.

Introduction

Analysis of the current state of project management shows a significant increase in the number of projects implemented in the spheres of construction, public administration, energy, consulting, and digital technologies. Professional project management allows to effectively allocate responsibilities and responsibilities between project participants, save money and time, reduce risks. Understanding the importance of future development, the heads of organizations are increasingly using project management methods to create competitive advantages, and in the applied theory of management of organizational systems, more attention is paid to the teamwork of the organization's personnel.

The organization of teamwork is one of the fundamental principles of project management, which involves the formation of teams, the organization of their effective work and interaction with the goal of uniting and coordinating the efforts of all the performers involved in the project.

The urgency and scientific significance of the issue

The problems of the formation and functioning of teams are investigated in sociology - in the works of R.M. Andreeva, T.P. Galkina, A.V. Zhutkina, K. Levina, A.I. Prigogine; psychology -in the works of V.V. Avdeeva, M.Yu. Gubieva, V.V. Isaeva, V.I. Kornienko, Yu.V. Sinyagin, K. Foppel, R. Chaldini, S. Tannenbaum, R. Beard, E. Salas; management - in the works of T.Yu. Bazarov, S.A. Barkalov [1, 2], P. Drakker, V.N. Mikheeva.

The results of the study of mathematical models of the formation and functioning of teams are

reflected in the works of B.N. Burkov [3], D.A. Novikova [4, 5], A.G. Chkhartishvili, V. Holmstrom, J. Marshak, R. Radner. The current state of mathematical models of the formation and functioning of teams includes several research directions: assignment models that use, in the main, the optimization apparatus for solving the tasks of forming the composition of teams, the distribution of roles and the scope of work; game-theoretic models; simulation models; Reflexive models using the apparatus of the theory of reflexive games.

An important task in the management of project teams is the formation of incentive systems for project team members. In this case, it is necessary to take into account the specifics of the project activity [1, 2]. To the conditions of the project it is unproductive to apply methods of stimulating current work. The task of the incentive system in project management is to ensure that the project is completed on time without additional budget expenditures. The calculation of incentive payments should be based on not only individual, but also team performance indicators.

When creating incentive systems for project team members, it is necessary to take into account the specifics of the project activity. To the conditions of the project it is unproductive to apply methods of stimulating current work. The task of the incentive system in project management is to ensure that the project is completed on time without additional budget expenditures. The calculation of incentive payments should be based on not only individual, but also team performance indicators.

In order to maintain the motivation of project team members, individual and unified incentive schemes are applied. The disadvantage of individual incentive schemes is, firstly, unequal conditions for encouraging different groups of performers, which can cause tension in the project team. Secondly, there is a danger of manipulation, that is, deliberate distortion of information on the amount of work and costs transferred from the members of the project team. In order to exclude distortion of information and reduce tension in the project team, unified incentive schemes apply when the incentive mechanism is the same for all performers. Intermediate position is occupied by group incentive schemes, when a number of project operations are divided into groups, for executors of each of which a unified incentive system is applied.

Formulation of the problem

Linear incentive systems use the linear function of the time of reduction of operations h¡ = Xa,, where X - the standard for reducing the duration, which is uniform for all operations, Ai - is the planned decrease in the duration of the i-th operations. In the spasmodic incentive system, the premium C to the performers of the operation does not depend on the magnitude of the reduction of the operation Ai and is the same for all transactions for which Ai > 0 .

We consider linear cost functions of the form

9 (x,) = A - ki X, i =1 n, where 9 < xi < Di, i = 1, n;

For a linear cost function, the minimum costs for performing an operation are equal Bi = Ai - kiDi, and the maximum costs Ni = Ai - kidi. Note that in the absence of stimulation, the duration of the i-th operation is Di, i = 1, n .

Let the project be a sequential chain of n operations. Let's assume that the operations are numbered in ascending order ki, i. e. k1 <k2 <... <kn. The value Di defines the standard duration of the i-th operation, and the value di - the minimum possible. It is necessary to build an optimal incentive system. For the construction of an optimal individual incentive system, we determine such a number j, that is

j-1 j

^ (Dt - dt) < 9 < ^ (Di - dt), where 0 = ^ Di - T - required reduction in proj ect duration. Operations

i=1 i=1 i

i = 1, j -1 and operations i = j +1, n scheduled duration xi = di. The planned duration of the operation j is

h (Аг-) = Фг (т°)-Фг (at).

(1)

T j = Dj-0+Z (D - d).

(2)

Determine the total amount of premiums.

The amount of bonuses for operations i = 1, j -1 is h = N - Bi = kt (D, - d,). The amount of bo-

nuses for operation j is hj = kj (Dj -x j) = kj A j = kj

e-X(D -J)

;=1

. The amounts of bonuses for

operations i = j +1,n are 0. The total amount of premiums is

H j k, (D, -x,) + k

e-^(D, - j, )

i=1

= kj e-^(kj - k, )(D, - j, ). 1

We construct an optimal unified incentive system.

Theorem 1. There is a unified system, such that the planned duration of operations for individual and unified incentive systems are the same, the standard X = kj, and the total amount of premiums is kj9 .

Evidence. Given a standard X the reduction in duration is possible for operations for which kj < X, that is, for operations for which the premium is not negative. It follows from condition (1) that X > kj, and hence the minimum X = kj. In this case, all operations for which kt <X the planned duration is obtained x, = dj. If there are several operations for which kt = X, then we assume that the planned duration

of all such operations except for the operation j, is equal to du and the planned operation time j is (2).

The theorem is proved.

The difference between the total premiums of the unified and individual incentive systems is

Hy -H = £(kj -k,)(D, -d,). 1

Jumping Unified Incentive Systems

Jumping unified incentive systems are characterized by the fact that premium C is the same for all operations for which xiJ- < DiJ- or AiJ- > 0 .

Let the premium value C be given. In this case, the task is to shorten the duration of the project to the required value so that the number of operations with Aij- > 0 s minimal. We show that this problem is

reduced to a discrete problem of optimizing the network by cost. For a given value of C the maximum reduction in the duration of the operation (i, j) is equal to

= min

V5'; C ,

V j /

(3)

Thus, the duration of each operation can take two values: the minimum value Dij with zero costs

(premium) and the minimum value

Ej = Dj

with costs (premium) C for any operation.

A task. Determine the duration of operations so that the duration of the project was no more (T- 9), and the costs were minimal.

Discrete optimization problems belong to the class of complex problems of discrete optimization. Consider the solution of this problem for aggregated networks. For this it is sufficient to consider a solution for a serial and parallel chain.

Decision. Order the operations in descending order n,. We define the minimal number of operations such that the sum n, is at least 9.

For independent (parallel) operations, the problem is solved more simply.

Solving problems for sequential and parallel operations, we get the dependence S(T) of the premium value from T for the whole aggregate project.

Example 1. Consider the network of Fig. 1 (operations are arcs). Data on transactions are shown in Table. 1.

Table 1

(i,./) (0, 1) (0, 2) (0, 3) (1, 4) (2, 3) (3, 4)

dij 1 1 1 2 1 3

D/ 4 2 3 3 3 5

S/ 3 1 2 1 2 2

Fig. 1

We will be limited to consideration of C-sy stems.

1 step. We consider sequential operations (0, 2), (2, 3). We have a dependence S (x)

т 2 3 4 5

с aggr 2с с с 0

2 step. We consider parallel operations (0, 3) and aggregated (0, 3). We have a dependence S03 (x03)

т 2 3 4 5

S 3c с c 0

3 step. We consider sequential operations (0, 1), (1, 4). We have a dependence S04(x04)

т 3 4 5 6 7

S 2c с c c 0

4 step. Consider sequential operations aggregated (0, 3) and (3, 4). We have a dependence S0(x04')

т 5 6 7 8 9 10

S 4c 4c 3c c c 0

5 step. We consider parallel operations (0.4) and (0.4') (both aggregated). We have a dependence S(T)

T 5 6 7 8 9 10

S 5c 5c 3c c c 0

The described algorithm can be used to obtain lower bounds, transforming an arbitrary network into an aggregate.

Group incentive schemes

Consider the problem of choosing the optimal group incentive system in the following formulation. A plan was drawn up to shorten the duration of the project, in which the duration and operations are reduced by A,- having the cost function coefficients K with a linear incentive system, the incentive rate is

X maxKj, and the incentive fund is

i

0 = X£A, . (4)

i

We will set the task of synthesizing the optimal group incentive system for a given number of groups m < n (it is clear that when we have an individual incentive system m = n). Let the norms be defined

X1 <X2 <... < X m = max Kl

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

i

for each group. We denote by Qj the set of operations for which Ki < X j.

Theorem 2. The j-th group includes operations of the set Qj \ Qj_1 (by definition Q0 = 0). Evidence. Let there be an operation S such that Ks < Xj, but S e Q1, where l > j. The award to the performers of the operation S is equal to Xl • AS . We transfer the operation S to the group j. In this case, the premium will be Xj • AS, less than Xl • AS . The theorem is proved.

To solve the problem, we define n + 1 vertex graph (network) with input 0 and output n (Fig. 2).

Fig. 2

Let K be numbered in ascending order, that is, K1 < K2 <... < Kn.

The arc i, j of the graph reflects the fact that the operations i + 1, m, j belong to one stimulus group, and the incentive standard in this group is Kj. Note that any path in a graph joining an input with an output and having m arcs determines uniquely the partition of operations into groups and the corresponding norms Xj. The reverse is also true, to any partition of the executors of operations in the team into incentive groups there corresponds a certain path in the graph connecting the entrance with the exit.

Define the arc length (i, j)

i =K i A,. (5)

S=i+1

We show that is equal to the fund for stimulating the group of operations (i + 1, m, j).

Indeed, the incentive standard for this group is Kj, and the total reduction in the durations of group

j

operations is i AS .

S=i+l

Consequently, the length of any path from the m arcs connecting the entrance to the exit is equal to the value of the incentive fund.

Task. Define m - is the path (the path containing m arcs) of minimal length.

This problem is a rather complex task of discrete optimization. Taking into account that the number of groups is usually small, the problem can be solved by brute force.

Example 2. The values Ki, i = 1, 7 are given in Table 2.

Let m = 3. We fix the value X1 = Ki and solve the problem for operations i + 1, ..., п and two groups.

The search of all possible X1 and allows to determine the optimal system for для m = 3.

Table 2

i 1 2 3 4 5 6 7

K 1 3 4 7 8 10 12

Ai 5 4 3 6 2 7 4

We assume that the group can not include only one operation.

1 step. X1 = 3.

X2 7 8

Ф 246 247

Optimum system X1 = 3, X2 = 7, Ф = 246. 2 step. X1 = 4.

X2 8

Ф 244

Comparing 3 options, we find the optimal incentive system:

^ = 4, Qi = (1, 2, 3);

= 8, Q2\QI = (4, 5); ^3 = 12, Q3\Q2 = (6, 7),

and a minimum incentive fund O = 244.

A similar problem can be solved for the C-stimulus system. Let the operations, the reduction values of their durations, and the coefficients K be given. The size of the premium is obviously equal to

C = max Kt At and the incentive fund O = C • n.

Let all operations be divided into m groups and numbered in ascending order Ki Ai, i. e. K1A1 < K2 A2 <... < KnAn. Let the bonuses be determined C1 < C2 <... < Cn = C = max Ki Ai . We denote by Qj the set of operations for which Ki Ai < Cj . Then it is obvious that

C = max K a, ,

j iQ i i

and the incentive fund is

The problem, like the previous one, reduces to determining the shortest m-paths in a graph with arc lengths

With a small number of groups, the problem, like the previous one, can be solved by exhaustive search.

Example 3. Take the data of Example 2. Number of groups m = 3.

1 step. Take the first group of operations (1, 2), C = 12.

We have two options for groups 2 and 3. In the first variant, the second group (3, 5) with C2 = 16, and the third (4, 6, 7) with C3 = 70. The incentive fund is

O = 2T2 + 2 16 + 3-70 = 266.

In the second variant, the second group (3, 5, 4) with C2 = 42, and the third (6, 7) with C3=70. The incentive fund is

O = 2T2 + 3-42 + 2-70 = 190.

2 step. Take the first group of operations (1, 2, 3), C = 12. There is only one option in the second group to include operations (5, 4) with C2 = 42, but in the third operation (6, 7) with C3 = 70. The incentive fund is

O = 3T2 + 2-42 + 2-70 = 260.

Optimal is the option (1, 2, 3), (5, 4), (6, 7) with the fund 260.

In this case, the group Z-system is more effective than the group C-system. However, we can cite problems in which the group C-system is more effective (for the same number of groups).

Group incentive systems occupy an intermediate place between individual systems and unified systems. They to some extent reduce the shortcomings of individual systems, as they generate competition both within groups and between groups and at the same time, as a rule, more effective than unified ones. The problem of constructing optimal group systems for arbitrary network graphs, and the development of effective algorithms for determining shortest paths with a fixed number of arcs are of interest.

(6)

j

where N Q, Qj-1) number of operations in the j-th group

lj = KjAj •(J -').

(7)

Conclusion

References

1. Barkalov S.A., Davydova T.E., Kalinina N.Yu., Kumosov V.B. Kompetentnostnyy podkhod v upravlenii personalom: otsenka, obuchenie, komandoobrazovanie [Competence Approach in Personnel Management: Assessment, Training, Teambuilding]. Voronezh, Nauchnaya kniga Publ., 2010. 184 p.

2. Barkalov S.A., Kalinina N.Yu., Nasonova T.V. [The Tasks of Increasing the Level of Competence of the Organization's Personnel]. Economics and Management of Management Systems, 2017, no. 3.1 (25), pp. 110-116. (in Russ.)

3. Burkov V.N., Korgin N.A., Novikov D.A. Kak upravlyat' proektami: nauchno-prakticheskoe izdanie [Introduction to the Theory of Management of Organizational Systems]. Moscow, Librokom Publ., 2009. 264 p.

4. Burkov V.N., Novikov D.A. Matematicheskie modeli formirovaniya i funktsionirovaniya komand [How to Manage Projects: Scientific and Practical Edition]. Moscow, SYNTHEG - GEO Publ., 1997. 188 p.

5. Novikov D.A. Stimulirovanie v organizatsionnykh sistemakh [Stimulation in Socio-Economic Systems]. Moscow, SINTEG Publ., 2003. 312 p.

Received 30 August 2018

УДК 658.3 DOI: 10.14529/^сг180415

СИСТЕМЫ СТИМУЛИРОВАНИЯ В УПРАВЛЕНИИ ПРОЕКТАМИ

С.А. Баркалов1, В.Н. Бурков2, Н.Ю. Калинина1, Т.В. Насонова1

1 Воронежский государственный технический университет, г. Воронеж, Россия,

2 Институт проблем управления им. В.А. Трапезникова Российской академии наук, г. Москва, Россия

Анализ современного состояния управления проектами показывает существенное увеличение количества проектов, реализуемых в сферах строительства, государственного управления, энергетики, цифровых технологий. Понимая важность будущего развития, руководители организаций применяют методы управления проектами для создания конкурентных преимуществ, а в прикладной теории управления организационными системами все большее внимание уделяется командной деятельности персонала организации.

Важная задача в управлении проектной командой - формирование системы стимулирования ее участников, задача которой - обеспечить выполнение проекта в срок без дополнительных расходов бюджета. В целях поддержания мотивации участников проектных команд применяются индивидуальные и унифицированные системы стимулирования.

Недостатком индивидуальных систем стимулирования является, во-первых, неравные условия поощрения различных групп исполнителей, а во-вторых, опасность манипулирования, то есть сознательного искажения информации об объемах работ и затратах, передаваемой от членов проектной команды. Для того чтобы исключить искажение информации и снизить напряженность в команде проекта, применяют унифицированные системы стимулирования, когда механизм стимулирования один и тот же для всех исполнителей. Промежуточное положение занимают групповые системы стимулирования, когда множество операций проекта разбивается на группы, для исполнителей каждой из которых применяется унифицированная система стимулирования.

В статье рассматриваются скачкообразные унифицированные системы стимулирования, и решается задача выбора оптимальной групповой системы стимулирования.

Ключевые слова: проект, команда, объединенные унифицированные системы стимулирования, групповые системы стимулирования.

Литература

1. Компетентностный подход в управлении персоналом: оценка, обучение, командообразо-вание / С.А. Баркалов, Т.Е. Давыдова, Н.Ю. Калинина, В.Б. Курносое. - Воронеж: Научная книга, 2010. - 184 с.

2. Баркалов, С.А. Задачи повышения уровня компетентности персонала организации / С.А. Баркалов, Н.Ю. Калинина, Т.В. Насонова // Экономика и менеджмент систем управления. -2017. - № 3.1 (25). - С. 110-116.

3. Бурков, В.Н. Как управлять проектами: науч.-практ. изд. / В.Н. Бурков, Д.А. Новиков. -М. : СИНТЕГ- ГЕО, 1997. — 188 с.

4. Новиков, Д.А. Математические модели формирования и функционирования команд / Д.А. Новиков. -М. : Изд-во физ.-мат. лит., 2008. - 184 с.

5. Новиков, Д.А. Стимулирование в организационных системах / Д.А. Новиков. - М.: СИНТЕГ, 2003. - 312 с.

Баркалов Сергей Алексеевич, д-р техн. наук, профессор, декан факультета экономики, менеджмента и информационных технологий, зав. кафедрой управления строительством, Воронежский государственный технический университет, г. Воронеж; barkalov@vgasu.vrn.ru.

Бурков Владимир Николаевич, д-р техн. наук, профессор, главный научный сотрудник, Институт проблем управления им. В.А. Трапезникова Российской академии наук, г. Москва; vlab17@bk.ru.

Калинина Наталия Юрьевна, канд. техн. наук, доцент кафедры управления строительством, Воронежский государственный технический университет, г. Воронеж; kalinina@vgasu.vrn.ru.

Насонова Татьяна Владимировна, канд. техн. наук, старший преподаватель кафедры управления строительством, Воронежский государственный технический университет, г. Воронеж; tnasonova@vgasu.vrn.ru.

Поступила в редакцию З0 августа 2018 г.

ОБРАЗЕЦ ЦИТИРОВАНИЯ

FOR CITATION

Incentive Systems in Project Management / S.A. Bar-kalov, V.N. Burkov, N.Yu. Kalinina, T.V. Nasonova // Вестник ЮУрГУ. Серия «Компьютерные технологии, управление, радиоэлектроника». - 2018. - Т. 18, № 4. -С. 152-159. DOI: 10.14529/ctcr180415

Barkalov S.A., Burkov V.N., Kalinina N.Yu., Nasonova T.V. Incentive Systems in Project Management. Bulletin of the South Ural State University. Ser. Computer Technologies, Automatic Control, Radio Electronics, 2018, vol. 18, no. 4, pp. 152-159. DOI: 10.14529/ctcr180415