Earned value management in project time control
Метод управления освоенным объёмом в контроле сроков
проекта
A.V. Vakhrushkina, A.V. Mishakova, K.D. Borshcheva,
Peter the Great St. Petersburg Polytechnic University, St. Petersburg, Russia
Студент А.В. Вахрушкина, студент А.В. Мишакова, студент К.Д. Борщева,
Санкт-Петербургский политехнический университет Петра Великого, г. Санкт-Петербург, Россия
Key words: method of management; earned value; project time control; planned value; actual cost; earned value management
Ключевые слова: метод управления; освоенный объём; контроль сроков проекта; плановый объём; фактическая стоимость; метод управления освоенным объёмом
Abstract. The paper is devoted to earned value management, it describes the basic tools of this method, particular attention is directed to the indicators of the deviation of the time of the project. Also reasons for not using the method in practice are revealed. The main problem of the method of earned value management - the impossibility of its application to project time control, analyzed ways to solve this problem, proposed by W. Lipke, were identified. As an example, a project consisting of 8 works was reviewed. It has been reviewed three cases of possible cost sharing between critical and non-critical activities. It is revealed that the method proposed by Lipke, is not suitable for the project, where the cost of critical activities is low. The conclusions are about the possibility of using the method for the project time control.
Аннотация. Статья посвящена методу управления освоенным объёмом, в ней описаны основные инструменты данного метода, особое внимание направлено на показатели отклонения сроков проекта. Также выявлены причины отказа от использования метода на практике. Выявлена основная проблема метода управления освоенным объёмом - невозможность его применения для контроля сроков проекта, проанализированы пути решения этой проблемы, предложенные У. Липке. В качестве примера был рассмотрен проект, состоящий из 8 работ. Было проанализировано три случая возможного разделения затрат между критическими и некритическими работами. Выявлено, что метод, предложенный У. Липке, не подходит для проектов, где стоимость критических работ невелика. Выводы содержат информацию о возможности использования метода для контроля сроков проекта.
Introduction
Current practice of the implementation of construction projects requires giving attention to the timeliness of work completion and commissioning of the object [1-3]. There are a number of projects for which the prevention of disruption of timing is very important, such as the Olympic objects in Sochi was necessary to complete and put in commission before the Olympic Games, football stadiums needed to build before the World Cup in 2018, etc [1-5]. Commissioning of these objects into operation later approved date (deadline) not only leads to a drastic reduction in the efficiency of the project, but often defeats the purpose of the implementation of the projects and can lead to the collapse of the program, which includes the project [6-9].
Therefore, when working with important projects, it is necessary to pay attention not only to the preparation and optimization of the calendar plan of the building, but also the formation of an effective system of monitoring, control and management of the project [10-15].
Practice of construction projects shows that the time of the completion of some of them can not be failure and timeliness of their implementation is an important management problem. However, some of the building projects realized in the "background" and the time of their completion is not important for project participants or the main criterion for the success of the project is to minimize the costs to the
detriment of the duration of the project [12-15]. But in this paper such projects are not considered. The main objects of study are the projects that have disruption of the schedule leads to serious catastrophic consequences.
However, joint control of the two most important parameters (time and cost) can be realized on the basis of the method of Earned Value Management. The basic principles of this method have been known and used in the industrialized countries in the late 1800s. In the early 1960s the US Air Force for the first time officially used the concept of Earned Value in the design and implementation of a unique project "Minute Man Missile". Due to the success of the application of this method has been introduced in the practice of project management and was legislated in the USA as mandatory for the implementation of projects [16].
Currently, there is little need to use the method of Earned Value Management both Russian and foreign practice in project management [17]. These experts in the field of application of the method of Earned Value Management as a K. Flemming and D. Koppelman give, in their opinion, the reasons for non-use of the method [17]:
- Method of Earned Value Management is not always and not for all is clear and can be difficult at first acquaintance with him.
- Method of Earned Value Management originally was to be used only for large systems and projects, such in the USA only 1 % of the projects using this method, and, in general, these projects involve the major systems of government.
- Method of Earned Value Management describes the current state of the project in some detail (which is not always satisfactory), and the management does not want to know all the negative information [17].
Due to state of this method in Russia it conducted a survey among experts project management sphere. Respondents should have been to give reasons for not using the method. The leader of the responses was the reason associated with the complexity of the link accounting systems and calendar planning. Also, the following reasons have been put forward: a lack of information on the practical application of the method of Earned Value Management and the absence of good reasons to use this method in the control of the project [16, 17].
However, the main reason for not using the method of Earned Value Management in practice is the impossibility of direct application to time control of the project [18]. Customer, first of all, interested in the project to be completed on schedule, that is, key information is how many days the execution of works is behind schedule (or ahead of him), and by using this method it is possible to determine the backlog in duration only in monetary terms. Therefore it is required to develop practical methods and algorithms for the application of this method in the time control [18, 19].
Methods
The method of Earned Value Management controls two important parameters of the project. These parameters are time and cost. Forecast of final duration and cost of the project can be obtained on the identified trends [18].
The main indicators of the method of Earned Value Management are [18, 19]:
- АС - Actual Cost.
- PV - Planned Value.
- EV - Earned Value.
In Figure 1 you can see a graphic image of the method of Earned Value Management. The planned value graphically represents the S-curve. It is a curve of planned distribution of cost (value) within the schedule from the beginning to the end of the work (project) [18, 19]. AC curve shows the actual money spent of the execution of the work (project) from the beginning to the actual date. The third curve EV shows money that has to be spent if the actually performed value of work (the project) to pay according to the plan [18, 19].
The graph shows the deviation of the time, cost and duration. The deviation of the curve AC from PV has cost variance (CV), determined by the formula:
CV=EV-AC, (1)
where CV - cost variance; EV - budgeted cost (earned value); AC - the actual cost.
If CV > 0, there is a budget saving, and if CV < 0 - cost overruns [20].
The deviation of the curve EV from PV has Schedule Variance (SV), but it is expressed in monetary units, that is, the difference between the cost of the executed and planned works, determined by the formula:
SV=EV-PV (2)
where SV - schedule variance; EV - earned value; PV - planned value [20].
If SV > 0 - the works are ahead of plan, and if SV < 0 - the works are lagging behind [20].
These two deviations can be calculated using the formulas and seen graphically. But the deviation of the duration (TV - Time Variance) is determined only graphically (Fig. 1) [20, 21].
Also relative indicators are introduced. Cost Performance Index is calculated as the ratio of the cost of executed works (EV) to actual cost (AC) and Schedule Performance Index is calculated as the ratio of earned value to the value which had to be done according to the schedule. If the CPI > 1, there is a budget savings, and if the CPI < 1 - cost overruns. Similarly, if the SPI > 1 - the works are ahead of schedule, and if the SPI < 1 - the works are lagging behind [18-21].
A PV/
AC^^ „ S -—, O / /
/ / >f col
)
/
L/
si
y . y x ______ EV
TV Time, $
PD Planned Duraiion
Figure 1. Graphical representation of Earned Value Management method
Also the Time Estimate at Completion (TEAC) may be determined based on the deviation in duration. Also the graph shows the planned parameters of the project: the planned budget of the project named Budget at Completion (BAC) and the planned duration of the project named Schedule at Completion (SAC) [19-22].
Results and Discussion
Compliance with deadlines is important in the implementation of construction projects. For some objects untimely completion of work could mean that the failure of the project. The method of Earned Value Management used for cost control can not be directly used to time control of the project. By this method to determine the backlog of the schedule can be graphically and in terms of money, but for the customer it is important to know that the backlog in days. The transition from the cost parameters to the time parameters is impossible because they have a fundamental difference: the final budget for the completion of the project consists of the cost of all work, and the project implementation time is determined by the critical path length, rather than the sum of the execution time of all the work [18-22]. Also, the time deviation indicators SV and SPI at the completion of the project with a delay do not indicate it [18-23].
This problem of the Earned Value Management method has been considered in the works of Walt Lipke, who developed the "Earned Schedule Concept", using time parameters [18, 19]. The essence of this method is to find the time for which the EV will be equal to PV [18, 19]. The indicator ES is entered and named Earned Schedule. It can be determined graphically (Fig. 2) and algebraically by the formula (3):
ES=C+I, (3)
where ES - time for which the EV will be equal to PV; C - the number of time periods for which the EV > PV; I - an increment, which is determined by linear interpolation of the period C + 1 by the formula (4):
/= (EV-PVJ
(PVC+1-PVC) ,
(4)
where I - the increment; EV - earned value; PVc; PVc + 1 - the planned values on the borders of the time period C + 1.
Then we can define indicators of the time deviation SV (t) and SPI (t), which will be determined by the formulas (5) and (6), respectively [18-21]:
SV(t)=ES-AT
(5)
where SV (t) - the time deviation, months .; ES - time for which the EV will be equal to the PV, months; AT - actual time months.
SPI(t)=ES/AT
(6)
where SPI (t) - the Schedule Performance Index; ES - time for which the EV will be equal to the PV, months; AT - actual time months.
If ES ahead ET, the SV (t) - is positive, and If ES is behind AT, the SV (t) - is negative. SPI (t) > 1, when ES exceeds AT, and SPI (t) < 1, when ES is smaller AT [18-21].
Figure 2. Graphical representation of the Earned Schedule Concept [23-25]
Let us try to test the theory of Walt Lipke by the example. Consider a project consisting of 8 works. (Fig. 3).
0 3.5 3 . 5
A
0.0 4.0 4.0
3.5 2.0 5.5
B
4.0 2.5 6.5 '
5.5 2.5 8.0 8.0 1.5 9.5
C F
6.5 3.5 10.0 10.0 2.0 12.0
5.5 2.0 7.5
D
6.5 2.0 8.5
9.5 1.5 11.0
I
12.0 2.0 14.0
3.5 4.0 7.5 7.5 1.0 8.5
E G
4.0 4.0 8.0 8.5 1.0 9.5
Figure 3. Project for an example
Parameters of the project work are shown in a Table 1. The project planned duration is 11 days, actual duration is 14 days, the critical path formed by the work A, B, C, F, I.
Table 1. Parameters of the project work
Work Duration Start Completion
A 3.5 0 3.5
B 2 3.5 5.5
C 2.5 5.5 8
D 2 5.5 7.5
E 4 3.5 7.5
F 1.5 8 9.5
G 1 7.5 8.5
I 1.5 9.6 11
Consider three cases: 1 case where the critical activities constitute the main cost of the project (that is, critical activities are much more expensive than non-critical), 2 case where the value of the critical activities is a small part of the total cost (that is, the critical works are cheap compared to non-critical) and 3 case - the cost of critical and non-critical activities about the same [23-27].
In all three cases, the planned cost of the project is 1 million, all non-critical activities are done in a timely, but the timing of non-critical activities is failure. For each of the cases the actual date is 7 days. The main task is to calculate the time deviation SV (t), the Schedule Performance Index SPI (t) and forecast the timing of completion of project.
Case 1. The critical activities constitute the main cost of the project
Table 2. The distribution of PV by status dates for case 1
Work Duration PV Days
1 2 3 4 5 6 7
A 3.5 100 28.57 57.14 85.71 100 100 100 100
B 2 300 0 0 0 75 225 300 300
C 2.5 250 0 0 0 0 0 50 150
D 2 30 0 0 0 0 0 7.5 22.5
E 4 40 0 0 0 5 15 25 35
F 1.5 150 0 0 0 0 0 0 0
G 1 30 0 0 0 0 0 0 0
I 1.5 100 0 0 0 0 0 0 0
Amount 1000 28.57 57.14 85.71 180 340 482.5 607.5
Table 3. The distribution of EV by status dates for case 1
Work Duration EV Days
1 2 3 4 5 6 7
A 4 100 25 50 75 100 100 100 100
B 2.5 300 0 0 0 0 120 240 300
C 3.5 250 0 0 0 0 0 0 35.725
D 2 30 0 0 0 0 0 0 7,5
E 4 40 0 0 0 0 10 20 30
F 2 150 0 0 0 0 0 0 0
G 1 30 0 0 0 0 0 0 0
I 2 100 0 0 0 0 0 0 0
Amount 1000 25 50 75 100 230 360 473.225
Table 4. The forecasting of the completion date project on the basis of EVM indicators for case 1
AT С I ES SV SV(t) SPI SPI(t) IEAC(t)
1 0 0.88 0.88 -3.57 -0.12 0.88 0.88 12.57
2 1 0.75 1.75 -7.14 -0.25 0.88 0.88 12.57
3 2 0.63 2.63 -10.71 -0.37 0.88 0.88 12.57
4 3 0.15 3.15 -80.00 -0.85 0.79 0.56 19.80
5 4 0.31 4.31 -110.00 -0.69 0.86 0.68 16.26
6 5 0.14 5.14 -122.50 -0.86 0.86 0.75 14.74
7 5 0.50 5.50 -134.28 -1.50 0.79 0.78 14.12
After analyzing the indicators, we see that the forecast is close to the actual duration. This means that the method of "Earned Schedule Concept" can be applied in this case.
Case 2. The cost of the critical activities is a small part of the total cost Table 5. The distribution of PV by status dates for case 2
Work Duration PV Days
1 2 3 4 5 6 7
A 3.5 15 4.2855 8.571 12.8565 15 15 15 15
B 2 0 0 0 0 0 0 0 0
C 2.5 0 0 0 0 0 0 0 0
D 2 350 0 0 0 0 0 87.5 262.5
E 4 300 0 0 0 37.5 112.5 187.5 262.5
F 1.5 5 0 0 0 0 0 0 0
G 1 320 0 0 0 0 0 0 0
I 1.5 10 0 0 0 0 0 0 0
Amount 1000 4.2855 8.571 12.8565 52.5 127.5 290 540
Table 6. The distribution of EV by status dates for case 2
Work Duration EV Days
1 2 3 4 5 6 7
A 4 15 3.75 7.5 11.25 15 15 15 15
B 2.5 0 0 0 0 0 0 0 0
C 3.5 0 0 0 0 0 0 0 0
D 2 350 0 0 0 0 0 0 87.5
E 4 300 0 0 0 0 75 150 225
F 2 5 0 0 0 0 0 0 0
G 1 320 0 0 0 0 0 0 0
I 2 10 0 0 0 0 0 0 0
Amount 1000 3.75 7.5 11.25 15 90 165 327.5
Table 7. The forecasting of the completion date project on the basis of EVM indicators for case 2
AT С I ES SV SV(t) SPI SPI(t) IEAC(t)
1 0 0.88 0.88 -0.54 -0.12 0.88 0.88 12.57
2 1 0.75 1.75 -1.07 -0.25 0.88 0.88 12.57
3 2 0.63 2.63 -1.61 -0.37 0.88 0.88 12.57
4 3 0,05 3.05 -37.50 -0.95 0.76 0.29 38.50
5 4 0.50 4.50 -37.50 -0.50 0.90 0.71 15.58
6 5 0.23 5.23 -125.00 -0.77 0.87 0.57 19.33
7 6 0.15 6.15 -212.50 -0.85 0.88 0.61 18.14
As a result of the calculation obtained that the forecast exceeds the actual duration of 4 days that is a false result. This means that the method of "Earned Schedule Concept" can not be applied in this case [26, 27].
Сase 3. The cost of critical and non-critical activities about the same
Table 8. The distribution of PV by status dates for case 3
Work Duration PV Days
1 2 3 4 5 6 7
A 3.5 125 35.7125 71.425 107.1375 125 125 125 125
B 2 125 0 0 0 31.25 93.75 125 125
C 2.5 125 0 0 0 0 0 25 75
D 2 125 0 0 0 0 0 31.25 93.75
E 4 130 0 0 0 16.25 48.75 81.25 113.75
F 1.5 125 0 0 0 0 0 0 0
G 1 125 0 0 0 0 0 0 0
I 1.5 120 0 0 0 0 0 0 0
Amount 1000 35.7125 71.425 107.1375 172.5 267.5 387.5 532.5
Table 9. The distribution of EV by status dates for case 3
Work Duration EV Days
1 2 3 4 5 6 7
A 4 125 31.25 62.5 93.75 125 125 125 125
B 2.5 125 0 0 0 0 50 100 125
C 3.5 125 0 0 0 0 0 0 17.8625
D 2 125 0 0 0 0 0 0 31.25
E 4 130 0 0 0 0 32.5 65 97.5
F 2 125 0 0 0 0 0 0 0
G 1 125 0 0 0 0 0 0 0
I 2 120 0 0 0 0 0 0 0
Amount 1000 31.25 62.5 93.75 125 207.5 290 396.6125
Table 10. The forecasting of the completion date project on the basis of EVM indicators for case 3
AT C I ES SV SV(t) SPI SPI(t) IEAC(t)
1 0 0.88 0.88 -4.46 -0.12 0.88 0.88 12.57
2 1 0.75 1.75 -8.93 -0.25 0.88 0.88 12.57
3 2 0.63 2.63 -13.39 -0.37 0.88 0.88 12.57
4 3 0.27 3.27 -47.50 -0.73 0.82 0.72 15.18
5 4 0.37 4.37 -60.00 -0.63 0.87 0.78 14.18
6 5 0.19 5.19 -97.50 -0.81 0.86 0.75 14.70
7 6 0.06 6.06 -135.89 -0.94 0.87 0.74 14.77
We see that the forecast is close to the actual duration. This is an acceptable result. This means that the method of "Earned Schedule Concept" can be applied in this case [26, 27].
Conclusions
Earned Value Management method used to control the cost of the project work, but it is equally important to control the time of the work execution. But for time control this method can not be applied directly. This is because the time control should be realized using time parameters, and Earned Value Management method uses cost parameters. This problem is trying to decide by applying the "Earned Schedule Concept" developed by Walt Lipke. But if critical works are inexpensive, this method can give a
false result. As a conclusion, we can say that require the development of practical algorithms and methods of using this method to time control of the project.
References
1. Kalugin Yu.B. Universalnyy metod vychisleniya dostovernykh srokov realizatsii proyekta [Universal method for calculation of reliable completion times]. Magazine of Civil Engineering. 2016. No. 7. Pp. 70-80.
2. Bovteev S.V., Kanyukova S.V. Razvitiye metodiki kontrolya srokov investitsionno-stroitelnogo proyekta [Development of methodology for time management of construction projects]. Magazine of Civil Engineering. 2016. No. 2. Pp. 102-112.
3. Bovteev S.V., Terentyeva Ye.V. Upravleniye srokami stroitelnykh proyektov [Construction project schedule control]. Project and Program Management. 2014. No. 2. Pp. 158-173. (rus)
4. Werkl M., Heck D. Coping with incompleteness: An approach using time and production related compensation. 6th International Structural Engineering and Construction Conference: Modern Methods and Advances in Structural Engineering and Construction. 2011. Pp. 279-284.
5. Schlagbauer D., Heck D. Change in output performance due to prolonged work. 7th International Structural Engineering and Construction Conference: New Developments in Structural Engineering and Construction. 2013. Pp. 1375-1380.
6. Urbanaviciene V., Kaklauskas A., Zavadskas E.K., Sliogeriene J., Naimaviciene J., Vatin N.I. Facilitating the housing bargaining with the help of the bargaining decision support system. International Journal of Strategic Property Management. 2014. No. 18(3). Pp. 213-224.
7. Ptukhina I.S. Metodika raspredeleniya ekonomicheskoy otvetstvennosti ispolniteley za zaderzhku okonchaniya stroitelstva. [Technique of distribution of economic responsibility of performers for delay in completion of construction]. Nauchnyy zhurnal KubGAU. 2011. No. 68(04). [Electronic resource]. System requirements: AdobeAcrobatReader. URL: http://ej.kubagro.ru/2011/04/pdf/35.pdf. (rus)
8. Bolotin S.A., Dadar A.Kh., Ptukhina I.S. Imitatsiya kalendarnogo planirovaniya v programmakh informatsionnogo modelirovaniya zdaniy i regressionnaya detalizatsiya norm prodolzhitelnostey proyekta [Simulation of calendar planning in Building information modelling programms and regression detailing of construction period rules]. Magazine of Civil Engineering. 2011. No. 7. Pp. 8286.
9. Abdullayev G.I. Vliyaniye organizatsionno-tekhnologicheskikh faktorov na effektivnost upravleniya stroitelstvom sooruzheniy [The influence of organizational and technological factors on management efficiency the construction of buildings]. Magazine of Civil Engineering. 2011. No. 2(20). Pp. 52-54. (rus)
10. Chulgayeva O.V., Chulgayeva V.S. Podgotovka biznes-plana investitsionno-stroitelnogo proyekta na osnove ekonomiko-matematicheskikh modeley [Preparation of the business plan of investment project on the basis of economic-mathematical models]. Magazine of Civil Engineering. 2009. No. 3. Pp. 61-64. (rus)
11. Bovteev S.V., Chayka Yu.O. Veroyatnostnoye planirovaniye stroitelstva obyektov [Probabilistic planning of construction projects]. Mir stroitel'stva i nedvizhimosti. 2006. Vol.14. Pp. 52-54.(rus)
12. Bovteev S.V., Chayka Yu.O. Metody kontrolya realizatsii stroitelnykh proyektov na osnove sovremennykh programmnykh sredstv [Methods of monitoring the implementation of construction projects on the basis of modern software]. Trudy SPbGASU. Technologia i Organizatsia Stroitel'nogo Proizvodstva [Technology and organization of construction industry]. Saint-Petersburg:
Литература
1. Калугин Ю.Б. Универсальный метод вычисления достоверных сроков реализации проекта // Инженерно-строительный журнал. 2016. № 7. С. 70-80.
2. Бовтеев С.В., Канюкова С.В. Развитие методики контроля сроков инвестиционно-строительного проекта // Инженерно-строительный журнал. 2016. № 2. С. 102112.
3. Бовтеев С.В., Терентьева Е.В. Управление сроками строительных проектов // Управление проектами и программами. 2014. № 2. С. 158-173.
4. Werkl M., Heck D. Coping with incompleteness: An approach using time and production related compensation / 6th International Structural Engineering and Construction Conference: Modern Methods and Advances in Structural Engineering and Construction. 2011. Pp. 279-284.
5. Schlagbauer D., Heck D. Change in output performance due to prolonged work // 7th International Structural Engineering and Construction Conference: New Developments in Structural Engineering and Construction. 2013. Pp. 1375-1380.
6. Urbanaviciene V., Kaklauskas A., Zavadskas E.K., Sliogeriene J., Naimaviciene J., Vatin N.I. Facilitating the housing bargaining with the help of the bargaining decision support system // International Journal of Strategic Property Management. 2014. № 18(3). Pp. 213-224.
7. Птухина И.С. Методика распределения экономической ответственности исполнителей за задержку окончания строительства // Научный журнал КубГАУ. 2011. № 68(04). [Электронный ресурс]. Систем. требования: AdobeAcrobatReader. URL: http://ej.kubagro.ru/2011 /04/pdf/35.pdf.
8. Болотин С.А., Дадар А.Х., Птухина И.С. Имитация календарного планирования в программах информационного моделирования зданий и регрессионная детализация норм продолжительностей проекта // Инженерно-строительный журнал. 2011. № 7. С. 82-86.
9. Абдуллаев Г.И. Влияние организационно-технологических факторов на эффективность управления строительством сооружений // Инженерно-строительный журнал. 2011. № 2. С. 52-54.
10. Чулгаева О.В., Чулгаева В.С. Подготовка бизнес-плана инвестиционно-строительного проекта на основе экономико-математических моделей // Инженерно-строительный журнал. 2009. № 3. С. 61-64.
11. Бовтеев С.В., Чайка Ю.О. Вероятностное планирование строительства объектов // Мир строительства и недвижимости. 2006. № 14. С. 52-54.
12. Бовтеев С.В., Чайка Ю.О. Методы контроля реализации строительных проектов на основе современных программных средств // Труды СПбГАСУ (Технология и организация строительного производства). СПб.: Изд-во СПбГАСУ, 2005. С. 128-135.
13. Болотин С.А., Климов С.Е. Рациональная адаптация программы Microsoft Project для цели статического моделирования несвоевременного выполнения работ // Труды СПбГАСУ (Технология и организация строительного производства). СПб.: Изд-во СПбГАСУ, 2005. С. 109-114.
14. Котовская М.А. Особенности теории ограничений систем Голдратта и метода критической цепи в области календарного планирования строительных проектов // Современные проблемы науки и образования. 2014. № 4. С. 234-235.
15. Lipke W. Project Duration Forecasting... A Comparison of Earned Value Management Methods to Earned Schedule //
SPbGASU. 2005. Pp. 128-135. (rus)
13. Bolotin S.A., Klimov S.Ye. Ratsionalnaya adaptatsiya programmy Microsoft Project dlya tseli staticheskogo modelirovaniya nesvoyevremennogo vypolneniya rabot [Rational adaptation microsoft project software for the purpose of statistical modeling of untimely execution of works]. Trudy SPbGASU. Technologia i organizatsia stroitel'nogo proizvodstva [Technology and organization of construction industry]. Saint-Petersburg: SPbGASU. 2005. Pp. 109-114. (rus)
14. Kotovskaya M.A. Osobennosti teorii ogranicheniy sistem Goldratta i metoda kriticheskoy tsepi v oblasti kalendarnogo planirovaniya stroitelnykh proyektov [Specific features of goldratt´s theory of constraints and critical chain project management in the scheduling of construction projects]. Modern Problems of Science and Education. 2014. No. 4. Pp. 234-235.(rus)
15. Lipke W. Project Duration Forecasting... A Comparison of Earned Value Management Methods to Earned Schedule. The Measurable News. 2009. Issue 2. Pp. 24-31.
16. Khomutinnikova K.S. Kriterii otsenki metodov kontrolya, ispolzuyemykh pri upravlenii stroitelnym proyektom [Evaluation criteria of controlling methods used in construction project management]. Project and Program Management. 2009. No. 4. Pp. 312-323. (rus).
17. Bovteev S., Petrochenko M. Method "Earned Value Management" for Timescale Controlling in Construction Projects. Applied Mechanics and Materials. 2015. Vol. 725-726. Pp. 1025-1030.
18. Lipke W. Earned Schedule Contribution to Project Management. PM World Journal. 2012. Vol. I. Issue II. Pp. 1-19.
19. Practice Standard for Earned Value Management 2th ed. Newtown Square, PA: Project Management Institute, 2011. 54 p.
20. Project Management Body of Knowledge 5th ed. Newtown Square, PA: Project Management Institute, 2013. 506 p.
21. Mishakova A., Vakhrushkina A., Murgul V., Sazonova T. Project control based on a mutual application of pert and earned value management methods. Procedia Engineering. 2016. Vol. 165. Pp. 1812-1817.
22. Hecht L. A Case Study of Earned Schedule to do Predictions. The Measurable News. 2007-2008. No. Winter. Pp. 16-18.
23. Henderson K. Further Developments in Earned Schedule. The Measurable News. 2004. No. Spring. Pp. 15-22.
24. Lipke W. A Study of the Normality of Earned Value Management Indicators. The Measurable News. 2002. No. Dec. Pp. 1-16.
25. Lipke W. Earned Schedule - Schedule Performance Analysis from EVM Measures. Projects & Profits. 2010. No. Jan. Pp. 53-61.
26. Lipke W. Earned Schedule - Ten years after. PM World Journal. 2014. Vol. III. Issue I. No. January. Pp. 1-11.
The Measurable News. 2009. Issue 2. Pp. 24-31.
16. Хомутинникова K.C. Критерии оценки методов контроля, используемых при управлении строительным проектом // Управление проектами и программами. 2009. № 4. С. 312-323.
17. Bovteev S., Petrochenko M. Method "Earned Value Management" for Timescale Controlling in Construction Projects // Applied Mechanics and Materials. 2015. Vols. 725-726. Pp. 1025-1030.
18. Lipke W. Earned Schedule Contribution to Project Management // PM World Journal. 2012. Vol. I. № II. Pp. 1-19.
19. Practice Standard for Earned Value Management 2th ed. Newtown Square, PA: Project Management Institute, 2011.
20. Project Management Body of Knowledge 5th ed. Newtown Square, PA: Project Management Institute, 2013.
21. Mishakova A., Vakhrushkina A., Murgul V., Sazonova T. Project control based on a mutual application of pert and earned value management methods // Procedia Engineering. 2016. Vol. 165. Pp. 1812-1817.
22. Hecht L.A Case Study of Earned Schedule to do Predictions // The Measurable News. 2007-2008. № Winter. Pp. 16-18.
23. Henderson K. Further Developments in Earned Schedule // The Measurable News. 2004. № Spring. Pp. 15-22.
24. Lipke W. A Study of the Normality of Earned Value Management Indicators // The Measurable News. 2002. № Dec. Pp. 1-16.
25. Lipke W. Earned Schedule - Schedule Performance Analysis from EVM Measures // Projects & Profits. 2010. № Jan. Pp. 53-61.
26. Lipke W. Earned Schedule - Ten 2017s after // PM World Journal. 2014. Vol. III. Issue I. Pp. 1-11.
Анна Викторовна Вахрушкина, +7(981)8186968;
эл. почта: anna.vahrushkina@mail.ru
Анастасия Вячеславовна Мишакова, +7(911)9075242;
эл. почта: nastya.misha14@gmail.com
Ксения Дмитриевна Борщева +7(921)4438710; эл. почта: ksenbor@icloud.com
© Vakhrushkina A.V.,Mishakova A.V.,Borshcheva K.D.,2017