Научная статья на тему 'UNIVERSAL METHOD FOR CALCULATION OF RELIABLE COMPLETION TIMES'

UNIVERSAL METHOD FOR CALCULATION OF RELIABLE COMPLETION TIMES Текст научной статьи по специальности «Строительство и архитектура»

CC BY
18
7
i Надоели баннеры? Вы всегда можете отключить рекламу.
Журнал
Magazine of Civil Engineering
Scopus
ВАК
RSCI
ESCI
Ключевые слова
CONSTRUCTION MANAGEMENT / PROJECT SCHEDULING / CRITICAL PATH METHOD / CIVIL ENGINEERING

Аннотация научной статьи по строительству и архитектуре, автор научной работы — Kalugin Yu.B.

Usually the actual duration of construction projects significantly exceeds the scheduled durations.The reason is the lack of realistic scheduling. This paper presents a universal method for computing the reliable completion time for a construction project with network plans that have imprecise durations. The study is based on the consecutive comparison and calculation of the time distributions for the fulfilment of construction events. The general applicability of the algorithm is demonstrated. The method was used for the calculation of a more realistic time span for the construction of a road. The network schedule is formed on the basis of the flow sheet. A comparison was drawn between the proposed method and traditional techniques. The mean duration of the technological process calculated by a universal method is 30% more than for a known critical path method. It is confirmed that the traditional method of calculating the time to complete a project is almost always shorter. The method and algorithm presented in this study used Microsoft Excel. The calculations lasted some seconds. Implementation of the universal method will allow for the determination of a more precise duration for the performance of complex works at the planning stage.The suggested methodology can be recommended for use by construction project managers.

i Надоели баннеры? Вы всегда можете отключить рекламу.
iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.
i Надоели баннеры? Вы всегда можете отключить рекламу.

УНИВЕРСАЛЬНЫЙ МЕТОД ВЫЧИСЛЕНИЯ ДОСТОВЕРНЫХ СРОКОВ РЕАЛИЗАЦИИ ПРОЕКТА

Обычно фактическая продолжительность строительных проектов значительно превышает запланированные сроки. Причина – отсутствие инструмента достоверного планирования. В статье представлена универсальная методика для вычисления надежного времени завершения строительных проектов на основе сетевых графиков с неопределенными продолжительностями работ. Исследование основано на последовательном сравнении и вычислении распределений сроков свершений совместных событий графика. Продемонстрирована общая применимость алгоритма. Метод использовался для вычисления достоверных сроков сооружения участка дороги, для чего на основе технологической карты был сформирован соответствующий сетевой график. Сравнение между предложенным подходом и традиционными методами показало, что средняя продолжительность технологического процесса, вычисленного универсальным методом, на 30 % больше, чем для известного метода критического пути. Подтверждено, что традиционный метод критического пути существенно занижает сроки реализации проекта. Метод и соответствующий алгоритм реализован в среде Microsoft Excel. Вычисления продлились несколько секунд. Внедрение универсального метода позволит определять достоверные сроки выполнения комплексов работ при планировании проектов. Предложенный подход может быть рекомендован для использования руководителями строительных проектов.

Текст научной работы на тему «UNIVERSAL METHOD FOR CALCULATION OF RELIABLE COMPLETION TIMES»

doi: 10.5862/MCE.67.7

Universal method for calculation of reliable completion times

Универсальный метод вычисления достоверных сроков

реализации проекта

Yu.B. Kalugin,

Military Institute of Rail Transport Troops and Military Communications, St. Petersburg, Russia

Key words: civil engineering; construction management; project scheduling; critical path method

Д-р техн. наук, профессор Ю.Б. Калугин,

Военный институт железнодорожных войск и военных сообщений, г. Санкт-Петербург, Россия

Ключевые слова: управление

инвестиционно-строительными проектами; расписание проекта; метод критического пути

Abstract. Usually the actual duration of construction projects significantly exceeds the scheduled durations.The reason is the lack of realistic scheduling. This paper presents a universal method for computing the reliable completion time for a construction project with network plans that have imprecise durations. The study is based on the consecutive comparison and calculation of the time distributions for the fulfilment of construction events. The general applicability of the algorithm is demonstrated. The method was used for the calculation of a more realistic time span for the construction of a road. The network schedule is formed on the basis of the flow sheet. A comparison was drawn between the proposed method and traditional techniques. The mean duration of the technological process calculated by a universal method is 30% more than for a known critical path method. It is confirmed that the traditional method of calculating the time to complete a project is almost always shorter. The method and algorithm presented in this study used Microsoft Excel. The calculations lasted some seconds. Implementation of the universal method will allow for the determination of a more precise duration for the performance of complex works at the planning stage.The suggested methodology can be recommended for use by construction project managers.

Аннотация. Обычно фактическая продолжительность строительных проектов значительно превышает запланированные сроки. Причина - отсутствие инструмента достоверного планирования. В статье представлена универсальная методика для вычисления надежного времени завершения строительных проектов на основе сетевых графиков с неопределенными продолжительностями работ. Исследование основано на последовательном сравнении и вычислении распределений сроков свершений совместных событий графика. Продемонстрирована общая применимость алгоритма. Метод использовался для вычисления достоверных сроков сооружения участка дороги, для чего на основе технологической карты был сформирован соответствующий сетевой график. Сравнение между предложенным подходом и традиционными методами показало, что средняя продолжительность технологического процесса, вычисленного универсальным методом, на 30 % больше, чем для известного метода критического пути. Подтверждено, что традиционный метод критического пути существенно занижает сроки реализации проекта. Метод и соответствующий алгоритм реализован в среде Microsoft Excel. Вычисления продлились несколько секунд. Внедрение универсального метода позволит определять достоверные сроки выполнения комплексов работ при планировании проектов. Предложенный подход может быть рекомендован для использования руководителями строительных проектов.

Introduction

The analysis of the current state of the theory and practice of scheduling illustrates the lack of realistic scheduling.

Therefore, the actual duration of various construction projects significantly exceeds the planned ones [1 -6].

The reason for the significant difference between planned and actual construction durations is, primarily, the impact on the works due to numerous stochastic factors [7]), which can be evaluated using probabilistic estimation [8-12].

The second reason is insufficiently reliable traditional PERT (Program Evaluation and Review Technique) method. The PERT method is generally intended for the calculation of schedules that have certain structures set by unambiguous technological processes. The activity time spans are assumed to follow a general Beta distribution [13-17].

There have been a number of studies [18, 19] that consider project scheduling and PERT using fuzzy logic for scheduling under uncertainty. Fuzzy logic has been proposed as an alternative approach for quantifying uncertainty related to project activity duration.

The traditional PERT method uses only the activity time means to calculate the critical path, reducing the stochastic model to a deterministic model. In PERT, three time estimates are required for each activity. The time estimates represent a pessimistic time, an optimistic time, and a most likely time for duration of the activity.

The method assumes that the sum of the mean completion times of activities on the critical path is normally distributed. This allows the calculation of the probability of completing the project within a given time period. A single critical path is thus calculated and relied upon, where in reality, there may be numerous possible critical paths that exist. For a large network plan the probability that any given path could be the critical path may be very small. PERT method yields results which are biased high. The construction project manager is thus grossly misled into thinking his chances are very good, when in reality they are very poor. If network has multiple parallel paths with relatively equal means, PERT calculations will be considerably biased [20]). As a result, the time to complete a project calculated by the traditional PERT method is almost always too short [21]).

Similar results have also been observed when using the technique of crashing PERT [22]). Completion times with the PERT method are much shorter than completion times calculated with the Monte Carlo method [15, 23, 24].

Methods

The problem of calculating a realistic duration for the completion of events is formulated as follows:

Activities i-j and i-k are performed in parallel (Fig. 1). Their late completion time defines the duration for the fulfilment of an event m (tm).

,m

Figure 1. The scheme for the calculation of t

Durations of performance of works of i-j and i-k are independent random variables (X and Y). The durations are characterized by distributions f (x) and f2(y).

The distribution of the function Z in Equation 1 is established as:

Z = max( X, Y). (1)

The problem is solved by using a universal DCI method (division, comparison, integration). The method is based on consecutive computing procedures listed as follows:

1. Parameters of the initial event of i are established. For the first event, (t, = 0).

2. The total area under a density curve is equal to 1 and divided by p, the number equal areas:

' О

5 = -

. P.

. The centre of gravity of each area is defined. These points will define p as equiprobable values of duration C^x2...xp_1,xp;yuy2...yf^yp) (Fig. 2).

Figure 2. Distributions of activities (i-j, i-k)

3. Equiprobable durations for the fulfilment of events of j are defined as:

tj = t' + x1 ;

t2 t + X2 ;

tJP-i =tl + tp = t1 + Xp.

(2)

4. Equiprobable durations for the fulfilment of events of k are defined as:

tl = t + y{;

(3)

tk = t' + y 2;

tp-i = t' + yp-i;

tp = t' + yp.

5. Completion times for event m are calculated. To this end, equiprobable durations for the fulfilment of an event j are compared in pairs to the equiprobable durations for the fulfilment of an event k. In each pair, the maximum value is chosen.

tfr = max(tj;tkr ),r = i...p;

tp,r = max(t2;tkr ),r = 1...p;

.. (4)

t;-i,r = max(tp-i;tkr ),r = 1...p; tmp,r = max( tp ; tkr ), r = 1...p.

The ascending numerical series is a result formed by p of the equiprobable values of the durations for the fulfilment of an event m (tf,tf,...,tf,...,tmp,_vt^ ), t^ < tf,5 = i...p2.

6. This series is consistently divided by p segments for the purpose of further calculation reduction.

Each segment includes p of values (tp1,...,tmp ;tp+1,...,tPp;•••;t(Pp-1)p,•••,tP )■ The integrated series

(tP, t 2 tp ) is f0rmed by the mean va|ues of each segment.

7. The equiprobable values of the duration of m-n (tpn,tpn,...,tpn) are defined (similar to 2).

8. The equiprobable durations for the fulfilment of events n are defined as,

jn _ jp . jpn . jn _ /P I fPn. • -fn _ fP I fPn .

t11 = t1 + t1 ; tl2 = t1 + 2 ;•••; t1 p = t1 + tp ;

n p pn n p pn n p pn

t21 = t2 ^ t1 ; t22 = t2 ' t2 ;•••; t2p = t2 ^ tp ;

••• (5)

n p pn n p pn n p pn

t(p-1)1 = tp-1 + t1 ; t(p-1)2 = tp-1 + t2 ;•••; t(p-1)p = tp-1 + lp ;

n p pn n p pn n p pn

tp1 = tp + t1 ; tp2 = tp + t2 ;•••;tpp + tp + tp •

2

The ascending numerical series is a result formed by p of the equiprobable values of the durations for the fulfilment of an event n (t^,t£,•••,t;,•••,t^t^2), t^ < tns,5 = 1...p2.

9. This series is consistently divided by p segments for the purpose of further calculation reduction. Each segment includes p of values (tf,...,tnp,...,tlp;...;tn^X)p,...,tnp2). The integrated series

(t1n, t n . ^ tp-1, tp ) is formed by the mean values of each segment-

Calculations for two parallel works of equal duration and standard normal distribution [25] (for p = 2, 4, 8, 10, 12, 14, 16, 32, 64, 128, 256, 512) showed the following result:

The true mean value of the duration for the performance of an event m did not exceed 0.56427

* 19 *

(n < 0.56427). At p = 12, n = 0.54025. The deviation from the true value (ju ) did not exceed 5 %. This indicates that this method is suitable for practical calculations of a network at p = 12 (Table 1). Table 1. Calculated equiprobable values for the fulfilment of event m

Parameters x

-1.7317 -1.1503 -0.8122 -0.5485 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

144 equiprobable values for the fulfilment of event m

-1.7317 -1.7317 -1.1503 -0.8122 -0.5485 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

-1.1503 -1.1503 -1.1503 -0.8122 -0.5485 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

-0.8122 -0.8122 -0.8122 -0.8122 -0.5485 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

-0.5485 -0.5485 -0.5485 -0.5485 -0.5485 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

-0.3186 -0.3186 -0.3186 -0.3186 -0.3186 -0.3186 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

-0.1046 -0.1046 -0.1046 -0.1046 -0.1046 -0.1046 -0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

0.1046 0.1046 0.1046 0.1046 0.1046 0.1046 0.1046 0.1046 0.3186 0.5485 0.8122 1.1503 1.7317

0.3186 0.3186 0.3186 0.3186 0.3186 0.3186 0.3186 0.3186 0.3186 0.5485 0.8122 1.1503 1.7317

0.5485 0.5485 0.5485 0.5485 0.5485 0.5485 0.5485 0.5485 0.5485 0.5485 0.8122 1.1503 1.7317

0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 0.8122 1.1503 1.7317

1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.1503 1.7317

1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317 1.7317

Integrated series. Mean = 0.54025 -0.907 -0.395 -0.122 0.105 0.301 0.472 0.614 0.812 1.038 1.15 1.683 1.732

The stated method used Microsoft Excel.

The distribution of parameters X (Y), Z (for events j (k), m) is presented in Figure 3.

Density was defined as the difference of adjacent equiprobable values (at half values for extreme intervals).

&

Jp

K<? A'b

x

□ event j (or k) □ event m

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

Figure 3. Distribution of parameters X (Y), Z (for events j (k), m)

Calculations show a shift of the maximum density to the maximum values Z.

Results and Discussion

The universal method presented in this paper was used to calculate a more realistic duration for the construction of a banquette of the road.

The technology and the organization of works are defined in the flow sheet [26]. According to the flow sheet the work process is performed in five divisions during one shift (Fig. 4).

# division 1 2 3 4 5

Processes 1. Paring 2. Consolidation of the basis of an banquette 1. Soil transportation bay dump trucks for the first layer of an banquette 2. Leveling of soil in an banquette the bulldozer 3. Dumping of soil 4. Consolidation of the first layer of an banquette 1 .Soil transportation bay dump trucks for the second layer of an banquette 2. Leveling of soil in an banquette the bulldozer 3. Dumping of soil 4. Consolidation of the second layer of an banquette l.Soil transportation bay dump trucks for the third layer of an banquette 2. Consolidation of the third layer of an banquette 3. Dumping of soil 4. Consolidation of the third layer of an banquette l.Soil transportation bay dump trucks for the upper layer of an banquette 2. Consolidation of the upper layer of an banquette 3. Dumping of soil 4. Consolidation of the upper layer of an banquette

Length, m 200 200 200 200 200

Machines, standard time (shift) 1.Bulldozer DZ-171 N1-2(0.7) 2.Tamping roller DU-101 N1-3 (0.2) Complex 1 1 .Dump track KAMAZ--55111 N1-36(0.5) 2.Bulldozer DZ-171 N3 (0.5) 3. Sprinkler MD 433-03 N1-3 (0.43) 4.Tamping roller DU-101 N1-3 (0.4) Complex 1 1.Dump truck KAMAZ--55111 N1-36 (0.46) 2.Bulldozer DZ-171 N3 (0.5) 3. Sprinkler MD 433-03 N1-3 (0.4) 4.Tamping roller DU-101 N1-3 (0.37) Complex 2 1.Dump truck KAMAZ--55111 N37-65 (0.53) 2.Bulldozer DZ-171 N4 (0.5) 3. Sprinkler MD 433-03 N4-5 (0.55) 4.Tamping roller DU-101 N4-5 (0.52) Complex 2 1.Dump truck KAMAZ--55111 N37-65 (0.49) 2.Bulldozer DZ-171 N4 (0.4) 3. Sprinkler MD 433-03 N4-5 (0.5) 4.Tamping roller DU-101 N4-5 (0,48)

7 6 » 5 | 4 m 3 2 1 '""'Î^^UU-lOINM \

\

DU-101N1-Î all but X —^ DU-101 Complex

N1-3 S,. \

\ DU-101N1-3 V

\ Complti^^---

DZ-171N1-2 alf but VV DU-101 W. Complex 2

\ N1-3

Direction of flow works <-

Figure 4. Fragment of flow sheet for the construction of a banquette

The network schedule was composed on the basis of the flow sheet (Fig. 5).

Division 1 Division 2 Division 3 Division 4 Division 5

200 m 200 m 200 m 200 m 200 m

Figure 5. Network schedule

The critical path (activities 1-9-20-27-36-40-42-43) is equal to 1.05 shifts. The stochastic parameters of the equipment [10] are presented in Table 2. Table 2. Stochastic parameters of equipment

Machines 12 equiprobable values standard time, shift t

Bulldozers 0.644 0.719 0.772 0.817 0.862 0.909 0.960 1.018 1.089 1.184 1.332 1.698 1.00

Tamping rollers 0.655 0.729 0.780 0.826 0.870 0.915 0.964 1.020 1.088 1.178 1.318 1.656 1.00

Dump rucks 0.691 0.761 0.809 0.851 0.891 0.932 0.976 1.026 1.085 1.161 1.277 1.541 1.00

Sprinklers 0.843 0.887 0.915 0.939 0.959 0.979 1.001 1.023 1.048 1.078 1.120 1.200 1.00

The stochastic parameters of the activities network schedule are presented in Table 3.

Table 3. Stochastic parameters of processes of construction of banquette

# activity Processes 12 equiprobable values time, shift t

Division 1

2-11 1.ParingDZ-171 N1-2 0.451 0.503 0.540 0.572 0.603 0.636 0.672 0.712 0.762 0.828 0.932 1.188 0.700

13-14 2. Consolidation of the basis DU-101 N1-3 0.131 0.146 0.156 0.165 0.174 0.183 0.193 0.204 0.218 0.236 0.264 0.331 0.200

Division 2

4-15 1. Soil transportation KAMAZ-55111 N1-36 0.346 0.381 0.405 0.426 0.446 0.466 0.488 0.513 0.543 0.581 0.639 0.771 0.500

5-16 2.Leveling of soil DZ-171 N3 0.322 0.359 0.386 0.408 0.431 0.454 0.480 0.509 0.544 0.592 0.666 0.849 0.500

6-17 3. Dumping of soil MD 433-03 N1-3 0.362 0.381 0.393 0.404 0.413 0.421 0.430 0.440 0.450 0.464 0.482 0.516 0.430

3-12 4. Consolidation of the first layer DU-101 N1-3 0.262 0.292 0.312 0.330 0.348 0.366 0.386 0.408 0.435 0.471 0.527 0.662 0.400

Division 3

24-30 1. Soil transportation KAMAZ-55111 N1-36 0.318 0.350 0.372 0.391 0.410 0.429 0.449 0.472 0.499 0.534 0.587 0.709 0.460

25-31 2.Leveling of soil DZ-171 N3 0.322 0.359 0.386 0.408 0.431 0.454 0.480 0.509 0.544 0.592 0.666 0.849 0.500

26-32 3. Dumping of soil MD 433-03 N1-3 0.337 0.355 0.366 0.375 0.384 0.392 0.400 0.409 0.419 0.431 0.448 0.480 0.400

23-29 4. Consolidation of the second layer DU-101 N1-3 0.242 0.270 0.289 0.306 0.322 0.339 0.357 0.377 0.403 0.436 0.488 0.613 0.370

Division 4

7-18 1. Soil transportation KAMAZ-55111 N37-64 0.366 0.403 0.429 0.451 0.472 0.494 0.517 0.544 0.575 0.615 0.677 0.817 0.530

8-19 2.Leveling of soil DZ-171 N4 0.322 0.359 0.386 0.408 0.431 0.454 0.480 0.509 0.544 0.592 0.666 0.849 0.500

9-20 3. Dumping of soil MD 433-03 N4-5 0.464 0.488 0.503 0.516 0.528 0.539 0.551 0.563 0.576 0.593 0.616 0.660 0.550

10-21 4. Consolidation of the third layer DU-101 N4-5 0.341 0.379 0.406 0.430 0.452 0.476 0.501 0.530 0.566 0.613 0.685 0.861 0.520

Division 5

34-38 1. Soil transportation KAMAZ-55111 N37-64 0.339 0.373 0.396 0.417 0.437 0.457 0.478 0.503 0.532 0.569 0.626 0.755 0.490

35-39 2.Leveling of soil DZ-171 N4 0.258 0.288 0.309 0.327 0.345 0.364 0.384 0.407 0.435 0.474 0.533 0.679 0.400

36-40 3. Dumping of soil MD 433-03 N4-5 0.422 0.444 0.457 0.469 0.480 0.490 0.500 0.511 0.524 0.539 0.560 0.600 0.500

37-41 4. Consolidation of the upper layer DU-101 N4-5 0.314 0.350 0.374 0.396 0.418 0.439 0.463 0.490 0.522 0.565 0.633 0.795 0.480

The stochastic parameters of the events network schedule were calculated by the universal method (Table 4).

Table 4. Stochastic parameters of events

# an of event 12 equiprobable values time, shift P(t)= 0.25 P(t)= 0.5 P(t)= 0.75

1 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

2 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

3 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

4 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

5 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

6 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

7 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

8 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

9 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

10 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

11 0.451 0.503 0.540 0.572 0.603 0.636 0.672 0.712 0.762 0.828 0.841 0.880 0.556 0.667 0.795

12 0.262 0.292 0.312 0.330 0.348 0.366 0.386 0.408 0.435 0.471 0.479 0.501 0.321 0.383 0.453

13 0.262 0.292 0.312 0.330 0.348 0.366 0.386 0.408 0.435 0.471 0.479 0.501 0.321 0.383 0.453

14 0.433 0.473 0.500 0.523 0.544 0.567 0.591 0.617 0.648 0.687 0.702 0.728 0.511 0.584 0.667

15 0.346 0.381 0.405 0.426 0.446 0.466 0.488 0.513 0.543 0.581 0.593 0.617 0.416 0.484 0.562

16 0.322 0.359 0.386 0.408 0.431 0.454 0.480 0.509 0.544 0.592 0.601 0.629 0.397 0.476 0.568

17 0.362 0.381 0.393 0.404 0.413 0.421 0.430 0.440 0.450 0.464 0.473 0.484 0.399 0.426 0.457

18 0.366 0.403 0.429 0.451 0.472 0.494 0.517 0.544 0.575 0.615 0.628 0.654 0.440 0.512 0.595

19 0.322 0.359 0.386 0.408 0.431 0.454 0.480 0.509 0.544 0.592 0.601 0.629 0.397 0.476 0.568

20 0.464 0.488 0.503 0.516 0.528 0.539 0.551 0.563 0.576 0.593 0.605 0.618 0.510 0.545 0.585

21 0.341 0.379 0.406 0.430 0.452 0.476 0.501 0.530 0.566 0.613 0.623 0.651 0.418 0.497 0.590

22 0.426 0.460 0.483 0.506 0.524 0.542 0.577 0.611 0.650 0.665 0.689 0.716 0.495 0.571 0.657

23 0.485 0.530 0.556 0.584 0.611 0.638 0.654 0.676 0.730 0.760 0.779 0.808 0.570 0.651 0.745

24 0.426 0.460 0.483 0.506 0.524 0.542 0.577 0.611 0.650 0.665 0.689 0.716 0.495 0.571 0.657

25 0.426 0.460 0.483 0.506 0.524 0.542 0.577 0.611 0.650 0.665 0.689 0.716 0.495 0.571 0.657

26 0.426 0.460 0.483 0.506 0.524 0.542 0.577 0.611 0.650 0.665 0.689 0.716 0.495 0.571 0.657

27 0.505 0.536 0.560 0.581 0.599 0.616 0.644 0.666 0.682 0.785 0.760 0.786 0.571 0.643 0.734

28 0.512 0.564 0.600 0.630 0.660 0.687 0.725 0.758 0.812 0.861 0.880 0.916 0.615 0.717 0.836

29 0.793 0.859 0.899 0.932 0.965 0.998 1.032 1.072 1.115 1.159 1.192 1.230 0.915 1.020 1.137

30 0.808 0.869 0.908 0.943 0.975 1.009 1.043 1.083 1.129 1.184 1.209 1.248 0.926 1.034 1.157

31 0.817 0.884 0.927 0.967 1.003 1.040 1.080 1.123 1.175 1.239 1.265 1.308 0.947 1.069 1.207

32 0.807 0.850 0.878 0.902 0.925 0.951 0.980 1.011 1.043 1.087 1.103 1.132 0.890 0.973 1.065

33 0.990 1.056 1.098 1.137 1.164 1.194 1.230 1.249 1.295 1.325 1.365 1.400 1.118 1.209 1.310

34 0.505 0.536 0.560 0.581 0.599 0.616 0.644 0.666 0.682 0.785 0.760 0.786 0.571 0.643 0.734

35 0.505 0.536 0.560 0.581 0.599 0.616 0.644 0.666 0.682 0.785 0.760 0.786 0.571 0.643 0.734

36 0.505 0.536 0.560 0.581 0.599 0.616 0.644 0.666 0.682 0.785 0.760 0.786 0.571 0.643 0.734

37 0.505 0.536 0.560 0.581 0.599 0.616 0.644 0.666 0.682 0.785 0.760 0.786 0.571 0.643 0.734

38 0.908 0.970 1.008 1.040 1.072 1.108 1.144 1.187 1.233 1.283 1.311 1.350 1.024 1.134 1.258

39 0.823 0.882 0.918 0.950 0.980 1.014 1.051 1.095 1.142 1.193 1.217 1.256 0.934 1.043 1.167

40 0.976 1.022 1.051 1.076 1.098 1.121 1.145 1.173 1.216 1.276 1.279 1.308 1.063 1.145 1.246

41 0.885 0.948 0.988 1.022 1.056 1.092 1.133 1.175 1.223 1.278 1.306 1.347 1.005 1.121 1.250

42 1.082 1.151 1.187 1.222 1.256 1.282 1.312 1.341 1.366 1.391 1.437 1.470 1.204 1.291 1.378

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

43 1.145 1.206 1.245 1.273 1.303 1.324 1.349 1.369 1.386 1.450 1.468 1.497 1.259 1.335 1.418

The distribution of completion times for the 43rd event is presented in Figure 6. 0.14

0.12 0.1 0.08 0.06 0.04 0.02

~I I I I I I I I I I I I I I I I I I I I I I I

t, shift

□ method PERT □ Universal method

Figure 6. Distribution of completion times (for the 43rd event)

The duration of the calculations lasted 3-4 s.

Using a known critical path method, the mean duration was equal to 1.05 shifts, while the mean duration was equal to 1.335 shifts with the universal method. With a probability of 0.75, construction works was scheduled to end after 1.418 shifts

Conclusions

1. The actual duration of various construction projects significantly exceeds the scheduled durations. The reason for the significant difference between planned and actual durations is, primarily, the impact of the numerous stochastic factors on the works. Additionally, the traditional PERT method uses a single critical path. As a result, the PERT method of calculating the time to complete a project is almost always too short.

The construction project manager is thus grossly misled into thinking his chances are very good.

2. The universal method to calculate an accurate duration for the fulfilment of events is presented. The basics of this universal DCI method (division, comparison, integration) include:

- The total area under a density curve (for parallel activities with a joint event) divides into p equal areas. The centres of gravity of each area will define p as equiprobable values of duration;

- Equiprobable completion times of one activity are compared in pairs to completion times of another activity. In each pair the maximum value is chosen. The ascending numerical series as a result is formed by the p2 of the equiprobable values of the duration for the fulfilment of an event;

- This series is consistently divided by p segments for the purpose of further calculation reduction. The integrated series is formed by the mean value of each segment.

Calculations for two parallel works of equal duration and standard normal distribution showed that this method is suitable for practical calculations of a network at p=12

The method presented in this study used Microsoft Excel.

3. The universal DCI method was used to calculate a realistic duration for the construction of a banquette of the road. The technology and the organization of works are defined in the flow sheet. According to the flow sheet, the works will be performed in five divisions during 1.05 shifts. With a traditional PERT method, the mean duration is also equal to 1.05 shifts. Using the universal DCI method,

Kalugin Yu.B. Universal method for calculation of reliable completion times. Magazine of Civil Engineering. 2016. No. 7. Pp. 70-80. doi: 10.5862/MCE.67.7

the mean duration is equal to 1.34 shifts; however, with a probability of 0.75 included, works will end after 1.42 shifts. The calculations lasted some seconds.

4. These results show the efficacy of the universal DCI method to calculate more realistic completion times. This method considers an increase in the actual completion times in comparison with the planned completion times (using the PERT method), especially since in reality, numerous possible critical paths may exist.

The suggested DCI method can be recommended for use by construction project managers in order to prevent a potential failure of project completion deadlines.

References

1. Afanasyev V., Afanasyev A. Potochnaya organizatsiya rabot v stroitelstve [Flowing organization works in construction]. Saint-Petersburg: SPbGASU. 2000. 169 p. (rus)

2. Bolotin S.; Birjukov A. Time management in drafting probability schedules for construction work. World Applied Sciences Journal. 2013. Vol. 23. No. 13. Pp. 1-4.

3. Bovteev S.V., Kanyukova S.V. Development of methodology for time management of construction projects. Magazine of Civil Engineering. 2016. No. 2(62). Pp. 102-112.

4. Sadi A., Sadiq A.-H. Causes of delay in large construction projects. Journal Project Management. 2006. No. 4(24). Pp. 349-357.

5. Simankina T., Sergeenkova O. Resource optimization of construction on a basis of the frontal and rhythmical stream. Applied Mechanics and Materials. 2015. Vols. 725-726. Pp. 984-989.

6. Trauner T., Manginelli W., Lowe J., Nagata M., Furniss B. Construction Delays: Understanding Them Clearly and Delay Analysis in Construction Analyzing Them Correctly. London, UK: Elsevier Inc. 2009. 288 p.

7. Kalugin Yu.B. Modelirovanie vozdeistviya destabiliziruyushchikh faktorov na tekhnologicheskii kompleks [Modeling of destabilizing factors of the technological complex]. News of Higher Educational Institutions. Construction. 2013. No. 7. Pp. 93-102. (rus)

8. Golenko-Ginzburg D.I. Stokhasticheskie setevye modeli planirovaniya i upravleniya razrabotkami [Stochastic models of network planning and management development]. Voronezh: Science Book. 2010. 284 p. (rus)

9. Golenko-Ginzburg D. On the distribution of activity time in PERT. Journal of the Operational Research Society. 1988. Vol. 39. No. 8. Pp. 767-771.

10. Maltsev Yu.A. Ekonomiko-matematicheskie metody proektirovaniya transportnykh sooruzhenii [Economic-mathematical methods of design of transport objects]. Moscow: Academia. 2010. 320 p. (rus)

11. Miller R. Schedule, Cost and Profit Control with PERT. McGraw-Hill. 1963. 58 p.

12. Rukovodstvo po razrabotke i primeneniyu veroyatnostnykh setevykh modelei v stroitel'stve [Guidelines for the development and application of probabilistic network models in construction]. Moscow: TsNIPIASS. 1979. 56 p. (rus)

13. A Guide to the Project Management Body of Knowledge. Project Management Institute. 2008. 506 p.

14. Birrell G. Construction planning beyond the critical path. Journal of Construction Division ASCE. 1980. No. 3(106). Pp. 389-407.

15. Golenko D.I. Statisticheskie metody setevogo planirovaniya i upravleniya [Statistical methods of network planning and management]. Moscow: Nauka. 1968. 400 p. (rus)

16. Mubarak S. Construction Project Scheduling and Control.

Литература

1. Афанасьев В.А., Афанасьев А.В. Поточная организация работ в строительстве. СПб: СПбГАСУ. 169 с.

2. Bolotin S.; Birjukov A. Time management in drafting probability schedules for construction work // World Applied Sciences Journal. 2013. Vol. 23. № 13. Pp. 1-4.

3. Бовтеев С.В., Канюкова С.В. Развитие методики контроля сроков инвестиционно-строительного проекта // Инженерно-строительный журнал. 2016. № 2(62). С. 102-112.

4. Sadi A.A. Sadiq A.-H. Causes of delay in large construction projects // Journal Project Management. 2006. № 4(24). Pp. 349-357.

5. Simankina T., Sergeenkova O. Resource optimization of construction on a basis of the frontal and rhythmical stream // Applied Mechanics and Materials. 2015. Vols. 725-726. Pp. 984-989.

6. Trauner T., Manginelli W., Lowe J., Nagata M., Furniss B. Construction Delays: Understanding Them Clearly and Delay Analysis in Construction Analyzing Them Correctly. London, UK: Elsevier Inc. 2009. 288 p.

7. Калугин Ю.Б. Моделирование воздействия дестабилизирующих факторов на технологический комплекс // Известия вузов. Строительство. 2013. № 7. С. 93-102.

8. Голенко-Гинзбург Д.И. Стохастические сетевые модели планирования и управления разработками. Воронеж: Научная книга. 2010. 284 с.

9. Golenko-Ginzburg D. On the distribution of activity time in PERT // Journal of the Operational Research Society. 1988. Vol. 39. № 8. Pp. 767-771.

10. Мальцев Ю.А. Экономико-математические методы проектирования транспортных сооружений. M.: Академия. 2010. 320 с.

11. Miller R. Schedule, Cost and Profit Control with PERT. McGraw-Hill. 1963. 58 p.

12. Руководство по разработке и применению вероятностных сетевых моделей в строительстве. М.: ЦНИПИАСС. 1979. 56 с.

13. A Guide to the Project Management Body of Knowledge. Project Management Institute. 2008. 506 p.

14. Birrell G. Construction planning beyond the critical path // Journal of Construction Division ASCE. 1980. № 3(106). Pp. 389-407.

15. Голенко Д.И. Статистические методы сетевого планирования и управления. М.: Наука. 1968. 400 с.

16. Mubarak S. Construction Project Scheduling and Control. Second Edition. New Jersey. Hoboken: John Wiley & Sons, Inc. 2010. 479 p.

17. Олейникова С.А. Критический анализ метода PERT решения задачи управления проектами со случайной длительностью выполнения работ // Системы управления и информационные технологии. 2013. T. 51. №1. С. 20-24.

18. Herroelen W., Leus R. Project scheduling under достоверных сроков реализации проекта //

Second Edition. New Jersey. Hoboken: John Wiley & Sons, Inc. 2010. 479 p.

17. Oleinikova S.A. Kriticheskii analiz metoda PERT resheniya zadachi upravleniya proektami so sluchainoi dlitel'nost'yu vypolneniya rabot [Critical analysis of the PERT method for solving the problem of project management with random duration of the work]. Control Systems and Information Technology. 2013. Vol. 51. No. 1. Pp. 20-24. (rus)

18. Herroelen W., Leus R. Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research. 2005. No. 165. Pp. 289306.

19. Liberatore M. Critical path analysis with fuzzy activity times. Journal of Transactions on Engineering Management. 2008. Vol. 55. No. 2. Pp. 329-337.

20. Klingel A. Bias in PERT completion times calculations for a real network. Management Science. 1966. Vol. 13. No. 4. Pp. 476-489.

21. Schonberger R. Why projects are always late: a rationale based on manual simulation of a PERT/CPM network. Interfaces. 1981. Vol. 11. No. 5. Pp. 66-70.

22. Haga W., O'Keefe T. Crashing PERT networks: A simulation approach. Proc. of the 4th International conference of the Academy of Business and Administrative Sciences Conference. Quebec City, Canada. 2001.

23. Burt J., Garman M. Conditional Monte Carlo: A simulation technique for stochastic network analysis. Management Science. 1971. No. 3(18). Pp. 207-217.

24. Van Slyke R. Monte Carlo methods and the PERT problem. Operations Research. 1963. Vol. 13. Pp. 141143.

25. Kalugin Yu.B. Universal'nyi metod otsenki srokov vypolneniya proekta s veroyatnostnymi vremennymi parametrami [Universal method of computing finish time for networks with imprecise durations]. News of Higher Educational Institutions. Construction. 2015. No. 1. Pp. 51 -59. (rus)

26. Tekhnologicheskie karty na ustroistvo zemlyanogo polotna i dorozhnoi odezhdy [Flow sheets on a construction of a road bed and a paving]. Moscow: ROSAVTODOR. 2004. 462 p. (rus)

uncertainty: Survey and research potentials // European Journal of Operational Research. 2005. № 165. Pp. 289306.

19. Liberatore M. Critical path analysis with fuzzy activity times // Journal of Transactions on Engineering Management. 2008. Vol. 55. № 2. Pp. 329-337.

20. Klingel A. Bias in PERT completion times calculations for a real network // Management Science. 1966. Vol. 13. № 4. Pp. 476-489.

21. Schonberger R. Why projects are always late: a rationale based on manual simulation of a PERt/CPM network // Interfaces. 1981. Vol. 11. № 5. Pp. 66-70.

22. Haga W., O'Keefe T. Crashing PERT networks: A simulation approach // Proc. of the 4th International conference of the Academy of Business and Administrative Sciences Conference. Quebec City, Canada. 2001.

23. Burt J., Garman M. Conditional Monte Carlo: A simulation technique for stochastic network analysis // Management Science. 1971. № 3(18). Pp. 207-217.

24. Van Slyke R. Monte Carlo methods and the PERT problem // Operations Research. 1963. Vol. 13. Pp. 141-143.

25. Калугин Ю.Б. Универсальный метод оценки сроков выполнения проекта с вероятностными временными параметрами// Известия вузов. Строительство. 2015. № 1. С. 51-59.

26. Технологические карты на устройство земляного полотна и дорожной одежды. М.: РОСАВТОДОР. 2004. 462 с.

Yuri Kalugin,