Научная статья на тему 'Beyond automation - esp optimization and runlife improvement process in occidental Ecuador'

Beyond automation - esp optimization and runlife improvement process in occidental Ecuador Текст научной статьи по специальности «Энергетика и рациональное природопользование»

CC BY
144
24
i Надоели баннеры? Вы всегда можете отключить рекламу.

Аннотация научной статьи по энергетике и рациональному природопользованию, автор научной работы — Waninger E., Zaruma M., Herrera F., Williams S.

Occidental Exploration and Production Company (OEPC) uses one hundred Electric Submersible Pumps (ESPs) to produce approximately 410,000 barrels of fluid (approximately 100,000 barrels of oil) from two producing areas in Ecuador's Block 15. In 2004, as part of a global automation process, hardware and software were installed to allow remote data acquisition and control, automated protection of the ESPs and semi automated diagnosis of well performance. After installation of the automation system, it became apparent that automated data collection and analysis would not in itself result in ESP optimization and runlife improvement. In order to achieve maximum improvement in monitoring, diagnosis, and analysis of well and ESP performance, it was necessary to train and coach OEPC and alliance partner staff in analytical techniques and use of the software.

i Надоели баннеры? Вы всегда можете отключить рекламу.
iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.
i Надоели баннеры? Вы всегда можете отключить рекламу.

Текст научной работы на тему «Beyond automation - esp optimization and runlife improvement process in occidental Ecuador»

УДК 550.43

АВТОМАТИЗАЦИЯ И ОПТИМИЗАЦИЯ НЕФТЕДОБЫЧИ В ЗАПАДНОМ ЭКВАДОРЕ

Э. Уонинджер, М. Сарума, Ф. Херрера, С. Виллиаме

Российский университет дружбы народов уп.Орджоникидзе, д. 3, 117419, Москва, Россия

Рассмотрено использование насосов для производства 100 ООО баррелей нефти от двух блоке в Эквадоре. Кроме этого для интенсификации добычи нефти были использованные современные аппаратные средства и программное обеспечение.

Introduction. Occidental Exploration & Production Company (OEPC) operates Block 15 in the east of Ecuador (fig. 1) through a participation contract with Petroec-uador (Ecuador's state oil company). Block 15 is an area of 494,000 acres located in the Amazonian rainforest in the Oriente Basin of northeastern Ecuador. Since commencing operation in Block 15 in 1985 OEPC has made commercial discoveries in the fields of: Indillana; Yanaquin-cha; Jivino; Laguna;

Napo; Itaya; Limoncocha; and Eden-Yuturi. OEPC produces a total of approximately 100,000 BOPD through two production facilities CPF and EPF (fig. 2).

The fields have multiple productive sands which are identified as Ml, М2, U, T and Hollin.

The sandstones are quartzite, fine to medium and medium to coarse, well sorted with normal grain size distribution, siliceous cementation with some kaolinite. The sands are of varying thicknesses in the different fields and in some areas are unconsolidated; permeability (250-2500 md) and porosity (13-22%) are considered to be good.

A highly active aquifer provides good pressure support but can result in early and rapidly increasing watercut in the wells. Tabl. 1 provides a summary of the range of

Fig. 1. Location of OEPC Block 15

operating conditions.

1

. ■■ '^ДЛ'-атиГ";

-<Э&СЗ* 7%«Й« *3

'. Ml ‘.Vi.:-;. 'I '

-...д».д||а<

У

Iril

даЛ^л#»»»т

Table 1

Block 15 Operating Conditions

QUANTITY FROM I TO QUANTITY FROM TO

#OF WELLS 100 CSG, O.D.(IN) & WT. 7 9,625

AVG. BFPD 1000 16000 TVD, FEET 6500 10000

SIBHP, PSI 2500 3800 MD, FEET 6500 14500

PUMP INTAKE PSI 600 1500 SCALE (LIGHT, ETC) No Yes

GOR, SCF/STKBBL 20 200 SAND No Yes

API 19 31 H2S No No

BHT, F 185 215 C02 (Wt % of reservoir fluid) 0,38 % 12%

TBG, O.D.(IN) 3,5 4,5 EMULSION (yes or no) No Yes

Overview of ESP Operations. Operations within block 15 are managed from offices at two processing facilities: CPF and EPF. EPF is the base for all Eden Yuturi operations and CPF the base for all of the other field operations (Indillana, Limonco-cha, Yanaquincha, Jivino, Laguna, Napo, Itaya).

To minimize environmental impact the wells are directionally drilled from pads. A typical pad may have as many as 15 wells. The oil from each pad is transported through a pipeline to the processing facility.

Each pad has well test facilities, newer pads have multiphase meters, older pads have a separator or wellcomp unit so that the production from each well can be measured. Each pad also has a chemical injection skid, power generation (CPF wells, EPF wells are supplied power from a central generation and Variable Speed Drives (VSDs) and transformers for each of the wells).

The wells are completed with 9 5/8” casing or 7” liner across the productive interval. Many of the wells are perforated in multiple sands but a downhole completion comprising downhole packers and sliding sleeves is often used to select the interval for production. Production tubing is normally 4.5” 12.7 lb/ft although there are some lower rate wells completed with 3.5” 9.2 lb/ft.

Well flowrates vary from 1000 BFPD to 16000BFPD. The pumps carried as standard inventory to meet this flowrate range are DN 1100, DN1750, G2700, GN3200, GN5200, GN5600, GN7000, SN2600, SN8500, JN10000 and JN16000. Seal units are

tandem units featuring a combination of labyrinth and bag modules. The motors are typically 562 dominator and range from 180 to 900 HP. The power cable is flat lead braided galvanized #1 5kV cable is used, often with a 3/8” capillary tube included for downhole chemical injection. Almost all of the ESP systems have a downhole sensor (measuring intake pressure) and a bypass (y-tool) system to allow access to change the producing interval or perform logs across the productive zone.

Automation Process. As part of a global automation process the Case Services system (csLIFT) for data acquisition and automation was installed in OEPC in early 2004. The system installed for OEPC has the following capabilities:

- acquire individual well and ESP operating parameters and store them in a database;

- view operating data in tabular or graphical format;

- configure alarms and trips such that when an operating parameter goes above or

below a set value an alarm can be activated or the equipment shut down;

- well test database for each well;

- production and downtime reporting;

- analysis of ESP and well performance (Subs Analysis).

After installation of the automation system the ESPs and wells were operated as they were prior to installation of csLIFT. ESPs continued to be run with local control at the VSD and protection being set based on traditional underload (85% stable current) and overload (120% stable current) settings.

On a theoretical level, application of automation to artificially lifted wells (level of

sophistication dependent) can result in the following five benefits:

1) obtain real time P&T downhole data (downhole sensors);

2) acquire downhole and surface data simultaneously (communication);

3) perform protection and alarming based on P&T (control);

4) get the data to where it can be used (communication and database);

5) use of data to optimize production (analysis and action).

Initially when OEPC implemented the automation system benefits 1, 2 and 4 were achieved - benefits 3 and 5 were not.

OEPC management recognized that in order to get the benefit from the automation system it was apparent that some additional action was going to be required!

The Training Process. A training process was implemented for OEPC, ePSolu-tions and ESP supplier personnel. The expense of training subcontactors was considered to be a key element in bringing about change - the desire being that everybody involved in operation of the ESPs has the same level of understanding and talks the same language.

Three batches of training were performed and resulted in over 30 people undergoing basic training. To bring about improvement of ESP operations it was necessary to show people why protection solely on electrical parameters does not benefit production optimization. It can be observed that amps (the top line) shows very little change despite the fact that production was decreasing. This undiagnosed problem, having occurred over a 6 month period, resulted in a loss of production of 40,000 barrels of oil. This well was protected with traditional overload and underload protection and monitored using a SCADA system. However, to diagnose the lost production requires an alarm on intake pressure followed by analysis of the pressure information.

Having reached this level of understanding it was then possible to develop a new protection philosophy based on pressures and temperatures as well as amps. In addi-

tion to developing a new protection philosophy of the ESP wells each of the classes generated a series of recommendations to improve the ESP operations. These recommendations form the basis for the section of this paper titled ‘Improvements to the ESP and Completion’. A second level of training was then implemented in order to teach the operations staff to use the Subs Analysis module of the automation package. The key aspects of this training were to:

- develop understanding of calculation process in Subs Analysis;

- process to validate input data (well test and completion);

- determine whether ESP is functioning correctly;

- validate well inflow (PI and Pr);

- analyze trends;

- determine levels for setting pressure and temperature alarms;

- know when production is being lost!

Following the course each attendee was assigned four wells to analyze. This was perhaps the most important part of the whole training process as this is the conversion of the theory to a tangible benefit to OEPC.

To analyze the wells the following procedure was applied:

1) validate input data for accuracy;

2) compare measured intake pressure to theoretical (ideal);

3) evaluate whether ESP is functioning correctly - if not, there is a need for quantifying its impact on production;

4) determine well inflow information for use in future design;

5) review ESP sizing vs. production rate and make recommendation for replacement ESP immediately in the event of failure;

6) establish value and set alarms on intake pressure, motor temperature and intake temperature.

A key focus of this process is to minimize lost or deferred production by always having the design and equipment ready for the next installation when the existing system fails. This means that a workover can be performed as soon as a rig is available, with no waiting for equipment. Presently, 46 wells had been thoroughly reviewed and alarms set, based on downhole sensor values. The findings from these wells were as follows:

- 65% of the wells had data incorrectly entered in csLIFT;

- 23,6% of the ESPS were out of range (13% of the ESPs were in downthrust, 10^6% of the ESPs were in upthrust);

- 28% of the wells had a problem resulting in loss of production and opportunity for optimization.

Automated ESP Protection. To move beyond the traditional approach of using electrical parameters to protect the ESP it is necessary to understand which additional parameters are useful. In OEPC the following parameters, in addition to current overload and underload, are used for protection of the ESP system: intake pressure; discharge pressure (when available); motor temperature; intake temperature.

Initially, when configuring these alarms a percentage basis of stable operating value was used as the basis for the alarm. However, due to the wide range of intake pressure (300-800) values and the fact that a 40 psi increase in intake pressure could result in a loss of production of 400 stblpd on a well with a PI of 10 stblpd/psi it was deemed more practical to set the alarms at intake pressure +/- 20 psi.

Prior to the training, the generally held view was that the motor temperature alarm should be set at the same value as the temperature specification at the motor. However, if we consider an ESP running in a well with a stable motor temperature of 180 degrees F, why should we wait for the motor to get to a temperature of 250 degrees F before shutting it down? If the motor has a steady operating temperature of 180 degrees F and it starts getting hotter, something is wrong! It is better to shut the ESP down than risk damaging the motor. OEPC now use a guideline of stable motor temperature +10 degrees for the alarm. No low motor temperature alarm is used.

The Well Analysis Process. There are many software tools that are marketed as being capable of performing ESP analysis and diagnosis. Most of these tools take a nodal approach to analysis of the system and always have to force the inflow and outflow at the node to match to achieve a solution. This procedure is effective for design but haS limitations whcii it COIiiSS to ailalySiS arid diagnOSiS Of ESP performance.

Consider the well test data shown in tabl. 2 where total liquid rate is declining and pump intake pressure is increasing, even though requency has been increased. Clearly there is a problem. But, is it a well inflow problem, a change in fluids, an ESP problem or well test measurement error?

Table 2

Well test data for a developing problem

Well Test Date WC Total Fluid Motor Hz Tubing Press Tubing Tmpr PIP (psi)

Oct 20 2004 24% 547 64 290 144 1344

Oct 18 2004 24% 1150 57 285 158 1146

Oct 16 2004 24% 1287 57 290 164 1035

Oct 12 2004 24% 1324 56 285 164 562

Oct 06 2004 28% 1429 56 280 160 549

Oct 02 2004 20% 1471 56 285 168 556

Most software would present an analysis of such an example as a pump curve and a system curve. The pump curve is a function of the pump type, number of stages and frequency of operation and the system curve is a function of fluid properties, wellhead pressure, friction, PI and reservoir pressure.

In order to simulate the data for the 20th of October (lower flowrate), the system curve would need to move to the left to intersect the pump curve at the lower flowrate or the pump performance would need to be de-rated (move down the system curve) or both! But which is it? Is there a well inflow problem, a pump problem or something else happening - there are many uncertainties.

Such an approach removes an unknown i.e. the well inflow (Pr and PI) from the calculation. Fig. 3, shows a graph of pressure vs. depth in the well, which will be called the Zorro Graph (or Gradient Traverse Plot)2. Looking at the graph and calculating from the top down, the steps can be summarized as follows.

J, PDP = THP + APhydrostatic + APfriction.

2. PIP = PDP - APpump.

Comparison of measured pump pressures to the ideal or calculated values is a powerful tool to determine whether the pump is working correctly. Any time the actual pump intake pressure is higher than the theoretical value this indicates that the pump has a problem (assuming the fluid properties and wellhead pressure have been vali-

dated).

Having determined whether the pump is working correctly, it is possible to calculate the flowing bottomhole hole pressure (FBHP), based on validated data as follows:

3. FBHP = PIP + APhydrostatic + APfiriction

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

The FBHP and reservoir pressure (SBHP) can then be used to determine the actual

PI of the well.

4. P, - SBHPFBHP

Rate STB day

There are a number of things that happen in the wells in question. Certain distinctions may be made by using diagnostic tools in order to establish the difference between a normally occurring event, which has to be accepted, and a problem (see

tabl. 3), which may be addressed

and rectified. Problems undiagnosed and not treated cause loss of production.

Improvements to the ESP and Completion. The ESP system design was originally developed and applied to the Indillana field. In order to manage the ESPs inventory four or five ‘standard’ ESPs were stocked. As new fields were discovered and produced e.g. Eden Yuturi, Limoncocha, etc., it has been found that different fields and wells have different behavior (sand, corrosion, scale producing).

Table 3

Comparison of natural events and problems

Natural Events Problems

Tubing head pressure change Frequency change Reservoir pressure decline Increasing watercut Bad well tests PI change (damage / sand control) Tubing restriction (scaling) Broken shaft (less pump stages working) Pump wear Gas interference Scaling perforations Scaled pump Plugged Intake Pump rotating in wrong direction Leaking y-tool blanking plug Hole in production tubing Pump off Pump wrong size Well to well interactions

CHPTHP

Fig. 3. The Zorro plot

These issues affect the ESP and require different subtleties of design to address the producing well conditions.

This dictates that a ‘standard’ design doesn’t work for all wells and in many cases customized designs are needed for specific well behavior.

Some of the solutions being applied or considered are shown in tabl. 4.

Table 4

Range of potential so utions for well specific issues

Problem Solution

Sand Improved sand control (gravel pack, mesh) Bearings with ceramic inserts More frequent placement of bearings Plnw nnmn l-X./VWV* * * r Improved (abrasion resistant) metallurgy Overstage the pump and run at lower speeds (rpm) Non return valve above pump

Corrosion Improved metallurgy Chemical injection (chemicals may require improved seal design)

Scaling Chemical Injection Mixed Flow Pump Stages Periodic acid / solvent treatments

For example, consider that a 100 stage GN4000, with tandem seal and 330 HP 1950Volt 102.5Amp 562 series motor is going to be installed in a well.

To perform a detailed design for this system some of the options that need to be examined are:

The PUMP:

What is the bearing material?

How often are the bearings placed?

What upthrust and downthrust protection is provided?

What is the metallurgy ie abrasion or corrosion resistant?

Are any coatings used?

What is the material of the elastomer seals between each stage (nitrile, aflas, viton)? What is the shaft strength?

Floating impellers or compression pump?

The SEAL:

How many chambers?

Connected in series or parallel?

Bag or Labyrinth for each chamber?

Upthrust bearing?

Which elastomers are used in the bag seal (can they resist, temperature, aro-matics and chemicals)?

Is the ESP in the vertical section - will labyrinth seals be effective?

Will the seals be effective in sand producing environment or will they plug? High load or standard load downthrust bearing?

The MOTOR:

What kind of protection (insulation) is provided on the windings?

Which motor dielectric oil used?

High temperature or high load bearings?

BHT and flowrate past the motor.

Single or tandem unit.

Most people do not have the required knowledge to assess this level of detail. Throw in cable and gas handling or processing issues and it becomes more challenging to develop a fit for purpose design. It is only through working in close cooperation with the ESP supplier that these issues can begin to be addressed.

There are many things that may be warranted on a high cost offshore ESP well to improve the chance of a long runlife that may not be justified onshore. In order to improve the runlife of the ESP system or improve OEPC’s ability to optimize production the following system improvements were identified,

- Use sensors with discharge pressure

- Acquire VSD frequency and wellhead pressure real time simultaneously with sensor parameters.

- Prevent excessive motor heating during startup by using a shroud or packer.

- Improve wellbore cleanout process.

- Ensure power quality study to determine level of harmonics, surge, sag, overvoltage, transients, etc.

- Evaluate ESPs installed in new drilled wells to determine whether ESP design appropriate - is there a need to test new wells to determine inflow before completion.

- Measure motor winding temperature (improved sensitivity compared to motor oil temperature) - ESP supplier to provide motors with motor winding thermocouple.

- Use round power cable to eliminate phase imbalance

- Use round cable all the way to pothead, eliminates MLE and splice.

- Use centralizers and clamps to protect larger round cable and ensure centralization. ESP Management Process. As part of our training process OEPC staff and alliance partners were constantly challenged to look at how things were being done and whether they could be done differently or better. This resulted in recognizing that the existing written procedures for management of the ESP operations did not reflect reality nor the ideal state.

In addition to implementing improved protection of the ESP system and performing real analysis of the ESP operating data the following improvements were identified as being required:

- more ESP engineering support in the office;

- more educated/trained ESP expertise within OEPC;

- more expertise for ESP supplier;

- standardization of procedures and practices between two operations (CPF and EPF);

- eliminate redundant data collection move to focus on genuine ESP runlife improvement (step changes) rather than just meeting the contract targets (gradual);

- improve investigation of failure analysis and action based on findings;

- revise roles and responsibilities for key positions.

The revision of operating procedures is on hold until some of the organizational, reporting and operational practices have been improved. As and when operations are aligned to best realistic practices the procedures manual may be rewritten.

ESP Operations Contract. The contract with our ESP supplier is based on a pay per day of operation for the ESP. The cost per day is derived from the price of the ESP system divided by the target MTBF. The target MTBF for the wells increases by a percentage for every year of operation over the four year contract. Payment for ESP operation commences after the ESP has been running for 150 days. The target runlife (TRL) escalates over the life of the contract as shown in fig. 4.

Some of the realities that were not envisioned when the contract was signed have been identified.

OEPC has pulled a number of ESP systems prior to failure to change zones, perform cement squeeze or stimulation.

There is no mechanism in the contract to compensate the supplier for equipment that is pulled before it reaches the target runlife.

Runlife does not necessarily relate to production. For example if we diagnose that a pump is doing 30% less than it should, due to wear, then we are losing production. The ESP supplier would like to leave the pump in the well as it is still running, thereby increasing the MTBF for the field. OEPC would rather replace the ESP and recover the lost production.

The MTBF is calculated on a field by field basis. It is easy to improve the runlife on the new fields which have very little historical data. It is difficult to impact the MTBF on the older fields3. See fig.5 and fig. 6.

The percentage improvement in runlife on an annual basis is not really a motivator for step changes in system runlife. Supposing the MTBF is 751 days but some of the wells achieve runlives of 1300 days. The contract calls for 818 days in the subsequent year but perhaps the driving force should be an aim to make all of the ESPs run for 1300 days.

The ESP supplier has made suggestions for design improvements. OEPC personnel chose not to implement them. What is the way forward? Implementation of the intent of the original contract has not been perfect on the part of OEPC nor the supplier. However, these issues are being addressed by working closely together and through honest communication on a technical and commercial basis.

A few guidelines for successful ESP contract management may be adopted.

The contract is a starting point for the relationship: as the relationship evolves, the contract will likely have to evolve.

A contract with truly aligned objectives probable needs to have a tie to production rather than ESP runlife.

If the relationship is not a win/win for both parties, it will not be a harmonious rela-

tionship. A supplier that is not making a reasonable profit cannot afford to dedicate the same resources (experience level, personnel) to improving a company’s operation. An operator that feels he has been exploited is unlikely to award the contract to the same supplier the next time around..

The operator NEEDS to have trained knowledgeable personnel with respect to ESP produced wells.

The ESP supplier needs to have trained knowledgeable personnel. ESP monitoring and diagnosis methods and techniques have evolved

- ensure your ESP supplier has too.

Conclusions. When OEPC installed an automation system, there was a perception that it would improve the day-to-day operation of the ESPs. However, in order to get the benefit from what is a good automation and analysis package, procedures have had to be changed.

The following provides a summary of OEPC’s main conclusions in going ‘beyond automation’.

1. Analysis has shown that the opportunity exists to increase production on 28% of OEPC Ecuador’s wells.

2. Automation in itself provides little or no advantage unless it is used to change the way that operations are managed.

3. Use collected data constructively by performing analysis,

4. The analytical process creates additional work - don’t expect automation to reduce the workload.

5. Alarms were set based on pressure and temperatures from the downhole sensor in addition to electrical (amps) protection. It has emerged that amps is insensitive to changes in many cases.

6. ESP diagnosis and analysis skills should be a core competency for the production engineers of any operator who intends to use ESPs. Don’t assume that the ESP supplier knows it all.

7. Coaching as well as training is required to bring about long lasting genuine change.

8. When performing analysis of measured pressure data, use a software tool or technique that allows separation of the wellbore pressure response from the reservoir inflow performance.

REFERENCES

1. “ESP Training and Competency Development in PDO” by Atika Al-Bimani, Nasser Al-Rawahy (Petroleum Development of Oman); Alastair Baillie, Sandy Williams (Engineering Insights Limited). Presented at ESP Workshop Houston 2004.

2. “Demystifying ESPs: A Technique to Make Your ESP Talk to You” by A. J. (Sandy) Williams. Presented at ESP Workshop Houston 2000.

3. “Making Sense of Mean Time Before Failure (MTBF) and Other Runlife Statistics” by Bruce Brookbank and Ken Bebak. Presented at ESP Workshop Houston 2004.

BEYOND AUTOMATION - ESP OPTIMIZATION AND RUNLIFE IMPROVEMENT PROCESS IN OCCIDENTAL ECUADOR

E. Waninger, M. Zaruma, F. Herrera, S. Williams

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

People’s Friendship University of Russia

Ordzhonikidze str., 3, 117419, Moscow, Russia

Occidental Exploration and Production Company (OEPC) uses one hundred Electric Submersible Pumps (ESPs) to produce approximately 410,000 barrels of fluid (approximately 100,000 barrels of oil) from two producing areas in Ecuador’s Block 15. In 2004, as part of a global automation process, hardware and software were installed to allow remote data acquisition and control, automated protection of the ESPs and semi automated diagnosis of well performance. After installation of the automation system, it became apparent that automated data collection and analysis would not in itself result in ESP optimization and runlife improvement. In order to achieve maximum improvement in monitoring, diagnosis, and analysis of well and ESP performance, it was necessary to train and coach OEPC and alliance partner staff in analytical techniques and use of the software.

Эрик Уонинджер (Eric Waninger), старший инженер-нефтяник компании OEPC (Оху) (США, Техас), специалист в области технологических процессов в нефтедобыче, член организации SPE.

Мартин Сарума (Martin Sigifredo Zaruma Torres), ведущий инженер RepsolYPF (Иран), в настоящее время - аспирант кафедры Нефтепромысловой геологии, горного и нефтегазового дела РУДН, в разные годы работал в нефтяных компаниях Bri-das, OEPC (Оху) и RepsolYPF. Специалист в области оптимизации продукции нефтяных скважин, применения систем автоматизации добычи нефти и др. Член организаций SPE и C1GMYP.

Франсиско Херрера (Francisco Herrera), мастер компании ОЕРС (Оху) (США, Техас), имеет большой опыт работы в области разработки и адаптации новых технологических процессов в нефтедобыче.

Санди Виллиаме (Sandy Williams), консультант производства компаний Worlwide и ALPERFORM (Великобритания), специалист в области технологических процессов в нефтедобыче, член организации SPE.

i Надоели баннеры? Вы всегда можете отключить рекламу.