A DATA-DRIVEN MULTI-CRITERIA DECISION-MAKING FRAMEWORK FOR INFRASTRUCTURE DEVELOPMENT PLANNING IN DEVELOPING COUNTRIES Текст научной статьи по специальности «Строительство и архитектура»

CC BY
22
10
i Надоели баннеры? Вы всегда можете отключить рекламу.
Ключевые слова
infrastructure / multi criteria decision making / analytic hierarchy process / construction industry

Аннотация научной статьи по строительству и архитектуре, автор научной работы — Yasir Mohammed Falih Alkharasani

Multi-criteria decision-making (MCDM) has turned into a decision support device for coordinating multiple specialized information and partner values in infrastructure the board. Different MCDM procedures and devices have been made. The Iraqi structure enterprises have experienced a large number of snags and troubles. Because of an absence of money, which is clear in the ventures' culmination taking surprisingly lengthy, deserted construction projects are quite possibly of the most common and basic issue in the Iraqi construction area. The objective of this examination is to pick the best type of association agreements to subsidize projects in Iraq utilizing the analytic hierarchy process (AHP) approach. Choosing the main variables for choosing a reasonable money methodology for the unwanted task utilizing a poll review. Using the Cronbach Alpha figured by SPSS programming, the dependability of the survey is laid out.

i Надоели баннеры? Вы всегда можете отключить рекламу.
iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.
i Надоели баннеры? Вы всегда можете отключить рекламу.

Текст научной работы на тему «A DATA-DRIVEN MULTI-CRITERIA DECISION-MAKING FRAMEWORK FOR INFRASTRUCTURE DEVELOPMENT PLANNING IN DEVELOPING COUNTRIES»

КОМПЬЮТЕРНЫЕ И ИНФОРМАЦИОННЫЕ ТЕХНОЛОГИИ

(COMPUTER & INFORMATION TECHNOLOGIES)

УДК 33

Yasir Mohammed Falih Alkharasani

Lobachevsky State University (Nizhny Novgorod, Russia)

A DATA-DRIVEN MULTI-CRITERIA DECISION-MAKING FRAMEWORK FOR INFRASTRUCTURE

DEVELOPMENT PLANNING IN DEVELOPING COUNTRIES

Abstract: multi-criteria decision-making (MCDM) has turned into a decision support device for coordinating multiple specialized information and partner values in infrastructure the board. Different MCDM procedures and devices have been made. The Iraqi structure enterprises have experienced a large number of snags and troubles. Because of an absence of money, which is clear in the ventures' culmination taking surprisingly lengthy, deserted construction projects are quite possibly of the most common and basic issue in the Iraqi construction area. The objective of this examination is to pick the best type of association agreements to subsidize projects in Iraq utilizing the analytic hierarchy process (AHP) approach. Choosing the main variables for choosing a reasonable money methodology for the unwanted task utilizing a poll review. Using the Cronbach Alpha figured by SPSS programming, the dependability of the survey is laid out.

Keywords: infrastructure, multi criteria decision making, analytic hierarchy process, construction industry.

1. INTRODUCTION

Over the last several decades, multi-criteria decision analysis has been used quite often. Its importance in several application fields has substantially expanded, particularly as new approaches are developed and as existing ones are enhanced. To rank the choices, multi-criteria decision-making (MCDM) offers a precise strategy for intertwining these contributions with benefit/cost information and decision-producer or partner viewpoints. To assess various game-plans, MCDM is utilized to

distinguish and evaluate decision-creator and partner worries about various (fundamentally non-financial) viewpoints. Various scholars guarantee that MCDM might be partitioned into two classes: multi-attribute decision-making (MADM) and multi-objective decision-making (MODM). Nonetheless, the terms MADM and MCDM frequently allude to similar class of models. Techniques like MCDM can possibly make these decisions more straightforward, analytically thorough, and auditable. The performance of alternative choice alternatives is evaluated or ranked using a number of criteria that are commonly quantified using various units.

Infrastructure management was used by both public and commercial organizations to manage and keep their aging and deteriorating infrastructure assets in excellent and usable shape. But because of rising demands, dwindling financial and human resources, and accelerated aging and degradation, sustaining the infrastructure system is more difficult than ever. Increased use and exposure to harmful environmental factors contributed to the rising degradation, and often, infrastructure systems have outlived their intended lifespans. Frameworks for dealing with the infrastructure have demonstrated to find actual success in overcoming any issues between client assumptions and the condition of the infrastructure.

Iraq, one of the United Nations' founding members, has endured protracted wars over the last forty years. As seen by the latest enormous scope youth shows that prompted an adjustment of organization, a developing public doubt in legislative establishments has added to shakiness, viciousness, and a common agreement that is very nearly imploding. Iraq will experience another cycle of instability unless the Iraqi government takes action to carry out significant changes that satisfy the expectations of the Iraqi people.

1.1. Conceptual Framework

Before the 2018 Kuwait Global Gathering for Reconstruction of Iraq, the World Bank surveyed that how much the destruction achieved by the fight against ISIL to be $88 billion. Not many of the responsibilities made at the Kuwait Worldwide Meeting for the remaking of Iraq have happened for various reasons, making this a suspicious wellspring of subsidizing for future reconstructing.

Iraq could modify or fix this obliterated infrastructure meanwhile utilizing its newfound oil cash, yet financial plan execution for non-oil consumptions, including reconstruction, was at a sad 18%, which is inadequate. From the get-go in 2022, the Service of Arranging made the declaration that no new venture activities will be added to the colossal excess of deficient undertakings. Infrastructure renewal and construction are also hampered by systemic governance issues including wasteful spending and corruption. It is necessary to address immediate repair and restoration, especially of infrastructure that is essential to the provision of fundamental services and economic activity. The UNDP Financing Office for Adjustment's achievements, which remembered 3,060 tasks for the energy, schooling, wellbeing, occupations, district, transport, sewage and water areas, traversing freed regions by December 2021 at an expense of more than $1 billion, act as one model.

1.2. Infrastructure Needs

For a long time, Iraq has had an extreme lodging deficiency. A deficiency of reasonable land for lodging in metropolitan regions has been exacerbated by partisan viciousness, an absence of chances for work, and commonly low thickness private metropolitan development, which has prompted an expansion in rents and land costs. The World Bank extended that notwithstanding the 2 million lodging shortfall that was accounted for in 2016, 138,000 private designs were obliterated as an outcome of the tactical battle with ISIL. As per gauges, the lodging industry will require uses adding up to around $17.4 billion to address the shortage inheritance and obliteration.

Beside the lodging shortage, different variables adding to the unrestrained development of casual settlements and underserved locales incorporate complex administration frameworks and processes for circulating area for the end goal of lodging, an absence of promptly accessible lodging credits, and obsolete ground breaking strategies for significant urban communities.

Addressing post-conflict housing needs An area-based, multi-sectoral, inclusive, and participatory strategy is required for Iraq. A temporary plan would advise development organizations and NGOs to keep serving the needs of those living in fast reparable partly damaged dwellings. In collaboration with the private

sector and commercial institutions, the government should develop a comprehensive plan for how to reconstruct devastated homes in the medium term (two to five years).

ISIL carried out a deliberate iconoclastic campaign throughout its occupancy, which resulted in the destruction of innumerable historical and religious monuments. The once multicultural and cosmopolitan city of Mosul was particularly hard hit. Over 80% of the old city was diminished to turned destruction throughout the span of four years. Neighborhood people group lost their places of love, social exchange, local area trust, discussion, and social cohesiveness because of this fiasco.

With a couple of verifiable locales and 120 old homes, rebuilding and recovery of social resources, including strict legacy, started in the Old City of Mosul in 2019. Over 7,218 historical fragments have so far been found. While work is still being done on the rehabilitation of 75 more homes as well as the rebuilding of all designated landmarks, the rehabilitation of 44 historic homes is almost finished, with the bulk of them having already been returned to their owners.

The restoration of legacy is a multifaceted intercession that goes past the genuine actual reconstruction of milestones. It likewise incorporates exercises to help the restoration of Mosul's social life, like live events, workmanship displays, film creation, supporting social and imaginative businesses, as a method for reestablishing social union, cultivate trust among individuals, and save Iraq's social legacy for people in the future. Support is additionally expected for Iraqi partners in the execution of social shows sanctioned by Iraq, like the 1970 Show against the Illegal Import, Product, and Move of Responsibility for Property and the 2003 Show for the Defending of Immaterial Social Legacy.

Throughout the course of recent years, Iraq's wellbeing framework has seen surprising difficulties and misfortunes. A populace that has lacking admittance to the crucial medical care administrations they need has been abandoned because of infrastructure harm and the departure of many prepared clinical staff. The nation is still recuperating from protracted periods of political unrest and violence while also dealing with significant issues. Despite the hostilities, Iraq's health outcomes have improved somewhat during the previous ten years.

The National Development Plan (NDP) 2018-2022, the Neediness Reduction Technique (PRS), the Reconstruction and Development Structure (2018-2027), and its Vision 2030 are only a couple of the undertakings being dealt with unfamiliar funders and development accomplices that are in accordance with the SDGs.

A National Committee on Sustainable Development (NCSD), managed by the Clergyman of Planning, was entrusted with following the SDGs' advancement and detailing back to a "significant level subsequent gathering" on the development of the nation. Particular subject committees (specialized groups) that attention on the numerous parts of sustainable development help the NCSD's operational exercises.

1.3. MCDM Approaches

In this part, we've attempted to provide a few succinct remarks on the fundamental concepts behind the different MCDM techniques. The basic explanations of the various techniques will be accompanied by relevant references, which readers may consult for in-depth technical presentations in order to create a self-contained paper. The following MCDM techniques will get the bulk of this discussion's attention:

• Weighted sum model (WSM)

• Weighted product model (WPM)

• Compromise programming (CP)

• Analytical hierarchy process (AHP)

• ELECTRE

• TOPSIS

• PROMETHEE

• VIKOR

The numerical components of the MCDM methods mentioned above are comparative in that values are relegated for options for every criterion, multiplied by matching loads, and afterward joined to create a complete score. As far as the points of interest of how criterion values are apportioned and mixed, the frameworks shift enormously. The strategies include particular information or information, and the subsequent scores have different numerical highlights and, consequently, fairly

changed values. Users often think that one of the several strategies is best because of the relative advantages and disadvantages of each one. In this part, MCDM approaches are briefly discussed and applied to the topic of infrastructure management.

• WSM and WPM

WSM is maybe the most utilized methodology, especially for issues with a solitary dimension. The best worth (most noteworthy for all advantage type criteria and least for cost-type criteria) of the weighted all out is what WSM alludes to as the ideal option. In view of the 'added substance utility' assumption, the model is intended for issues where all factors have a similar actual size. Additionally, for legitimate application, the criteria should be all cost-type or all-benefit-type. These elements cause it to seem unsatisfactory for issues that frequently involve many criteria and factors.

WPM and WSM are quite similar. The primary distinction is that weighted parameters are multiplied rather than added together. A series of ratios, one for each criterion, are multiplied to compare one possibility to the others. Every proportion is expanded to a power equivalent to the connected criterion's overall weight. WPM is sometimes referred to as dimensionless analysis since there are no units of measurement in its structure.

When accurate and complete information is acquired, WSM and WPM procedures may be used and are widely understood. They also perform well when compared to more complicated approaches. Multi-dimensional issues need normalization, which might be seen as a methodological flaw.

• Compromise Programming

Zeleny (1982) originally created CP, a technique for dealing with issues of a hierarchical nature, and Bardossy, Bogardi, and Duckstein (1985) subsequently expanded it to become composite programming. CP is a member of the category of 'distance-based' multi-criteria analytical approaches. Distance-based methodologies are expected to track down non-ruled solutions that, by some distance metric, are nearest to an optimal solution. The fundamental benefit of this approach is that it has

a straightforward conceptual framework. CP may be used to both decision analysis and mathematical programming (design problems).

• Analytic Hierarchy Process

Saaty (1980) first suggested AHP, which is based on determining preferences or significance weights for the criteria and alternatives. This approach allows for the hierarchical structuring of both the criteria and the options. The fundamental objective of the issue is at the highest point of the hierarchy, trailed by the criteria at the second level and the decisions at the third level.

• ELECTRE

Benayoun et al. (1966) are credited with fostering the primary ELECTRE strategy (Elimination Et Choix Traduisant la REalite). It is commonly alluded to as "ELECTRE I" on the grounds that few distinct iterations of the ELECTRE strategy were consequently evolved, including ELECTRE II, ELECTRE III, ELECTRE IV, ELECTRE Will be, ELECTRE A (which was created to address a particular decision issue for a huge financial organization however was kept confidential), and ELECTRE TRI. One of them, ELECTRE III, is the most well-known and often used. Although they are operationally relatively similar, all ELECTRE versions are based on the same basic ideas. The foundation of ELECTRE is the notion of outranking relations between alternatives, considered in pairs.

• TOPSIS

Hwang and Yoon (1981) created the Technique for Order of Preference by Similarity to Ideal Solution (TOPSIS), which is an application of a value-based compensating strategy. The TOPSIS technique seeks to choose options that are both closest to the positive ideal solution and the farthest away from the negative ideal solution. While the negative-ideal solution optimizes the cost criterion and decreases the benefit criteria, the positive-ideal solution maximizes the benefit criteria.

• PROMETHEE

Brans (1982) were quick to make the Inclination Positioning Organization Technique for Advancement Evaluations (PROMETHEE), and Wheats and Vincke (1985) developed it. PROMETHEE is an outclassing approach for positioning and

picking among contending criteria a little collection of elective actions. In any event, when clear and valuable information is required, PROMETHEE might be utilized. It depends on contrasting options while considering how every elective digresses from every prerequisite.

• VIKOR

Opricovic (1998), Opricovic and Tzeng (2002, 2003), what's more, Opricovic were essentially responsible for making the VIKOR strategy. Expecting that compromise can be satisfactory for conflict resolution, this technique is intended to tackle MCDM issues with conflicting and non-commensurable (attributes with various units) criteria. At the point when the decision-creator needs a solution that is as near the ideal solution as could be expected, the options can be assessed by completely settled criteria.

• Hybrid Methods

Opricovic (1998), Opricovic and Tzeng (2002, 2003), what's more, Opricovic were basically responsible for making the VIKOR procedure. Expecting that compromise can be satisfactory for conflict resolution, this strategy is intended to tackle MCDM issues with conflicting and non-commensurable (attributes with various units) criteria. At the point when the decision-producer needs a solution that is as near the ideal solution as could be expected, the choices can be assessed by totally settled criteria.

1.4. Types of MCDM Applications

In infrastructure the board, seven various types of MCDM applications have been found:

• Water resources systems: This involves evaluating strategy choices and creating both short-and long-term well defined courses of action for water assets such stream bowls, watersheds, and dams.

• Water and wastewater mains: For the administration of drinking or new water, wastewater, or sewage distribution, MCDM is particularly utilized in these examinations.

• Transportation: These studies focus on paving, highways, rail transportation, and roads.

• Bridges: These studies focus on the planning, building, upkeep, administration, and evaluation of bridges.

• Buildings: This involves applying MCDM to resolve issues with structures like elevated structures and multi-lodging edifices.

• Underground infrastructure: This involves utilizing MCDM to oversee underground infrastructure, including gas and petrol pipelines, passages, and tram frameworks.

• Others: Applications in metropolitan infrastructure, metropolitan seepage frameworks, seaward treatment facility plants, fundamental infrastructure, and so on are canvassed in these examinations.

2. LITERATURE REVIEW

Manupati, V. K., Ramkumar, M., &Samanta, D. (2018): In accordance with the Public authority of India's obligation to construct shrewd urban communities, this paper looks to lay out a system for metropolitan rejuvenation for the development of Indian urban areas. We lay out 7 criteria and 27 sub-criteria, for the most part from the writing connected to socio-specialized perspectives, to coordinate practices connected with the board of metropolitan regions and work on approach making decisions and logical investigation in this area. We give a multi-criteria decision-making (MCDM) strategy in light of the Decision Making Preliminary and Evaluation Research center based Analytic Organization Process (DANP) to deal with the relationships between the chose criterion and sub-criteria.

Erdogan, S. A., Saparauskas, J., &Turskis, Z. (2019): A suitable model will be developed in this essay. The research's extensive set of criteria was used to develop a construction management decision-making model, which was then used to analyze a case study involving Turkey. Calculations were performed utilizing the Analytic Hierarchy Process (AHP) procedure and the Master Decision PC application. The article rapidly goes through the wording and topic of overseeing construction projects. It portrays how multi-criteria strategies might be utilized to

resolve the essential issues in construction the board. One of the critical fixings in each large sustainable task's prosperity is viable administration.

Jena, R., Pradhan, B., &Beydoun, G. (2020): This exploration utilizes an analytical hierarchy process, a VIseKriterijumskaOptimizacija I KompromisnoResenje procedure, and a geographic information framework to dissect the tremor weakness appraisal (EVA) in Banda Aceh. North Sumatra's Banda Aceh City is close to the Incomparable Sumatran Shortcoming. Social, primary, and geotechnical weakness files were made utilizing different factors. By utilizing pair-wise comparison at all levels, the acknowledged philosophies were then consolidated and used to gauge the criteria weight, need requesting, and choices of criteria. To ascertain the seismic weakness file and make the weakness map, weakness layers were at long last layered. The middle region of the city shows high to very high helplessness, as indicated by the outcomes.

Abdullah, A. K., & Alshibani, A. (2022): This paper attempts to give a system to the decision of private accomplices in Saudi Arabia's lodging area under the concept of public-private organization. A system for selection in view of loads and utilities is worked by looking at criteria from a careful writing survey and specialists' contribution through overviews, then fostering additional studies consolidating decision-making strategies like the analytical hierarchy process (AHP) and multiattribute utility theory (MAUT). The discoveries uncovered four classes of criteria — monetary (C1), specialized (C2), administrative (C3), and security/environmental (C4) — as well as their sub-classifications. In view of the specialists' emotional appraisals, the exploration found that the essential elements were genuinely comparative in importance, with the specialized and security/environment criteria tied at 27%, trailed by the administration criteria at 24%, and the monetary criteria at 22%.

Bivina, G. R., &Parida, M. (2020): Involving an analytical hierarchy method to lay out need for some factors that impact walkers' decision of strolling, the flow research works on comprehension of the decision-making process of people on foot. To recognize passerby needs for strolling qualities inside four fundamental criteria —

wellbeing, security, solace and convenience, and portability and infrastructure — a questionnaire study was conducted in ten zones of Thiruvananthapuram City (Kerala, India). As indicated by the review, walker infrastructure plan component "Portability and Infrastructure" was not viewed as being as critical by people on foot as "Security," which was. In addition, this study distinguished a likely strategy for assessing the meaning of subjective elements that influence person on foot decision-making. To comprehend people on foot's decision-making process better, the review's outcomes underlined the worth of walker arranged evaluation. These discoveries will help metropolitan planners and different professionals in ordering the criteria characterizing the hierarchy of person on foot prerequisites and allotting assets for passerby conveniences as per the requests and expectations of walkers.

Nguyen, L. C., &Notteboom, T. (2016): In this study, a conceptual framework for the inclusion of several factors in the assessment of the placement of dry ports in developing nations from the viewpoint of various stakeholders is presented. In four phases, we provide the framework. The first phase is doing basic study to screen potential sites for the building of a dry port. The stakeholders are grouped into three categories in the second step: dry port consumers, dry port service providers, and the larger community. Then, we discuss the sub-criteria for dry port site along with the relevant measurement techniques. An explanation of the techniques used to weigh these criteria and sub-criteria is provided in the third stage. The last phase is doing a multi-criteria analysis.

Askarifar, K., Motaffef, Z., &Aazaami, S. (2018): This research is being done to assess investment potential in the area, to pinpoint the infrastructures that are required, and to encourage entrepreneurial endeavors. By contrasting 22 venture prospects, the strategy positions their probability of being carried out in Mokran utilizing the best-most exceedingly terrible multi-criteria decision technique (BWM) and the opinions of specialists. The expected public infrastructure is then reviewed utilizing TOPSIS into eleven classes. As indicated by the discoveries, the public area's planning needs are infrastructure, security, transportation, sustainable energy, and single-window taxpayer supported organizations. Confidential port destinations,

shipping bays, stockrooms, business focuses, and exceptional fisheries regions additionally show guarantee for financial backers.

Amorocho-Daza, H., Cabrales, S., Santos, R., &Saldarriaga, J. (2019): For human social orders to thrive economically and socially reasonably, dependable admittance to clean drinking water is fundamental. To pick amongst possible options for new water supply infrastructure, a multi-criteria decision examination (MCDA) strategy is expected for this work. These options are laid out for an extended lifetime and address considerable monetary assets. This examination laid out a MCDA method that consolidates a hierarchy of non-economic benefits and the expected expenses into an overall record to help decision-making in the context of growing new water supply infrastructure. In the Colombian city of St Nick Marta, our method was utilized. This city desperately needs to build its ability to satisfy the rising water need since it presently has a 60% drinking water shortage. The discoveries of this investigation empower the adoption of the most ideal option for settling St Nick Marta's water supply issue while considering partner interests.

3. METHODOLOGY AND EXPERIMENTAL WORK

The creators will frame the examination's procedure and give instances of the contextual analysis in this part.

3.1. Methodology

As displayed in Figure 1, the creators of this study will depend on interviews, questionnaires, factual information examination, and, at long last, the application of the AHP decision-making strategy to choose the best model and decide the best systems for improving the supporting execution of construction projects. The two essential components of philosophy are as per the following:

1. Part one (theoretical study):A review of prior research is undertaken in many areas related to this study, including partnership, abandoned/unfinished projects, and the use of AHP technology.

2. Part two (practical study):The empirical investigation comprised:

• Having discussions about the subject with engineers, specialists, and professionals employed by building businesses in order to develop a questionnaire for the research.

• Laying out significant norms and options for picking the sort of PPP contracts for building projects in light of examination and master counsel, as demonstrated in Table 1.

• Formulation and construction of an organized questionnaire that actions the significance of every one of the decided criteria for the other options. Professionals addressing all features of structural designing, including analysts, consultants, contractors, modelers, specialists, originators, and others, were reviewed to confirm the relative loads for and criteria. By using SPSS programming (Version 26) information examinations, the factual examination was finished to rush the discoveries. Cronbach's alpha was utilized to decide the rightness of the acquired information.

• Professionals working in the general population and confidential areas of the Iraqi construction industry (as a contextual analysis in Diyala Governorate) are given the questionnaire that was made explicitly for this reason and utilized in a field study to assemble information. With an expected response pace of 93%, 80 respondents gave a sum of 75 substantial answers.

• Examination of the positioning utilizing the Super Decisions program and the effect of the criteria on every one of the five contract classes (BOOT, BOT, BOO, DBFO, Traditional Confidential Contracts). The expected computations might be performed with extraordinary exactness and exact outcomes utilizing Super Decisions programming, which depends on the AHP approach.

Start

s. Practical Study Theoretical Study

—1—, —1—,

s. Collection of Data V. Introduction

—1—I —1—>

Identifying criteria and alternatives 4. Types of contract

—1—, -'-,

Formulating Questionnaire Analytic Hierarchy Process (AHP)

Statistical Analysis of results

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

Figure 1. Framework of methodology

Table 1. Criteria and alternatives overview

Criteria Alternatives

Risk Allocation and Sharing Build, Operate and Transfer (BOT)

Efficiency in cost and time management Build-Own-Operate-Transfer (BOOT)

Available Financial Market Build-Own-Operate (BOT)

Political support Design-Build-Finance-Operate (DBFO)

Quality Improvement Traditional Private Contracts

The Economic Framework That Was Created

A Powerful Private Consortium

Financial Benefit

Transparent Procurement Procedure

Integrated Project Delivery

Effectiveness Of Workplace Safety Management

Transfer Sustainable Approaches And Technologies

3.2. Experimental Work

The model proposed on the ventures will be utilized in the examination for this review. The Diyala Region project was picked as a contextual investigation, and information on the structure project was assembled from the public authority of Diyala's master engineers. This undertaking, the Al-Razi Complex, involves many designs. The size and style of each and every design is interesting. Because of the country's economic emergency and the security situation at that point, construction work on the undertaking was halted in 2013. These troubles can essentially affect construction projects, particularly in certain nations like Iraq. 4. RESULTS AND DISCUSSIONS 4.1. Specific information for the respondent Socioeconomics of the objective respondents show in Table 2

Table 2. Respondent profile

Information About Categories Percentage

Gender Males 75%

Females 25%

Academic qualification diploma 10%

bachelor 50%

Masters 20%

Ph D 15%

Other 5%

Group (Job) Architect 20%

Civil Engineer 50%

Electrical Engineer 15%

mechanical engineer 10%

other 5%

Specialization consultants 14%

designer 11%

site engineers 65%

project managers 10%

Practical experience (years) less than 5 years 40%

5-10 years 30%

11-15 years 18%

16-20 years 12%

4.2. Measuring the Reliability of Research Tool Using SPSS

The unwavering quality of the questionnaire in this exploration was confirmed by utilizing the Alpha Cronbach strategy to examine the information given by 75 respondents. The discoveries were 0.85, and the way that this worth is inside as far as possible approves the unwavering quality of the questionnaire. Table 3 shows how the alpha Cronbach coefficient classifies the level of constancy.

Table 3. Cronbach's alpha

Cronbach's alpha Degree of Reliability

a > 0.9 Excellent

0.9 > a > 0.8 Good

0.8 > a > 0.7 Acceptable

0.7 > a > 0.6 Questionable

0.6 > a > 0.5 Poor

0.5 > a Unacceptable

4.3. AHP results

In this review, the Super Decisions programming was utilized to break down the AHP results.

4.4. Total weight of every criterion and weight of every item

Utilizing the Super Decisions program, a couple wise comparisons of the overall loads of all evaluation criteria was utilized to decide the loads of the different criteria. The absolute weight of every criteria and the heaviness of everything are displayed in Table 4 separately. The 8.7% Consistency Proportion (CR) is upheld by the information. However long the inside consistency proportion (CR) in AHP is under 10%, the information got are reliable and consistent.

Table 4. The partnership method's weights for each criteria and item

Options Number of criteria

1 2 3 4 5 6 7 8 9 10 11 12

BOT 0.262 0.244 0.257 0.259 0.230 0.281 0.258 0.297 0.257 0.271 0.268 0.264

BOOT 0.198 0.180 0.172 0.181 0.126 0.164 0.165 0.134 0.145 0.164 0.107 0.135

BOO 0.128 0.209 0.178 0.232 0.189 0.224 0.216 0.201 0.233 0.258 0.259 0.214

DBFO 0.220 0.141 0.224 0.102 0.224 0.204 0.233 0.084 0.170 0.192 0.136 0.130

Traditional Private Contracts 0.189 0.224 0.167 0.224 0.229 0.125 0.126 0.282 0.192 0.113 0.228 0.254

4.5. Priorities of criteria and alternative

Two formats of the data are shown: normalized and limiting. The normalized values are in the range of 0 to 1, demonstrating the relative merits of each contracting strategy.

Table 5. Consequences of the Needs of option

BOT BOO Traditional Private Contracts DBFO BOOT

Normalized 0.261 0.213 0.193 0.175 0.157

Limiting 0.13 0.078 0.106 0.087 0.096

Although scaled down, the limiting numbers are also normalized, suggesting that they may reflect a more constricted or limited viewpoint.

0,3 0,25 0,2 0,15 0,1 0,05 0

Normalized Limiting

BOT BOO Traditional DBFO BOOT Private Contracts

Figure 2. The aftereffects of the Needs of option

4.6. Normalized Analysis

• BOT has the highest normalized score of 0.261, indicating that it is thought to be the most important or effective contracting strategy out of the available alternatives.

• BOO comes in second with a normalized value of 0.213, suggesting a somewhat lesser significance or performance than BOT.

• Traditional Private Contracts rank third in terms of importance or performance with a standardized value of 0.193.

• DBFO, with a normalized value of 0.175, comes in fourth place.

• BOOT has the lowest normalized value of 0.157, indicating that out of the five options, people think it is the least significant or effective.

4.7. Limiting Analysis

• BOT has the highest normalized score of 0.261, indicating that it is thought to be the most important or effective contracting strategy out of the available alternatives.

• BOO comes in second with a normalized value of 0.213, suggesting a somewhat lesser significance or performance than BOT.

• Traditional Private Contracts rank third in terms of importance or performance with a standardized value of 0.193.

• DBFO, with a normalized value of 0.175, comes in fourth place.

• BOOT has the lowest normalized value of 0.157, indicating that out of the five options, people think it is the least significant or effective.

5. CONCLUSION

To characterize every original copy into various gatherings, a categorization structure was made. The absolute number of articles distributed in the infrastructure the board discipline has essentially expanded across all application regions. Since infrastructure the executives issues are multidisciplinary in nature, it's a good idea that applications in asset the board, technique or planning development, and partner commitment are progressively predominant. Clients can resolve confounded issues in an in fact sound and basically practicable way by applying decision examination utilizing MCDM systems. Subsequently, the ascent of MCDM-based infrastructure the board frameworks may be viewed as a positive pattern. It has been found that, by and large, the main few options were the equivalent paying little mind to which MCDM procedures are utilized, regardless of the likelihood that different focusing on of the board choices could prompt a similar issue through application of various MCDM approaches. We actually see considerable likenesses in their main a few prospects in a couple of occasions when the top option was unique. Additionally, it has been shown that as the quantity of conceivable outcomes rises, these cross-over

decreases. Analysts picked MCDM methods over other decision-making systems as a result of their capability to increment decision-producers' transparency, analytical meticulousness, auditability, and limit with respect to conflict resolution.

Zeroing in on late monetary emergencies and showing their effect by halting or abandoning projects because of an absence of assets is one of the greatest difficulties confronting the construction area in non-industrial countries like Iraq. This has created a huge setback for the completion of ventures in Iraq. To finish the venture and forestall cost overwhelms, the creators are hence endeavoring to decide the best techniques for choosing the best financing model for public-private organizations utilizing AHP innovation. The creators reach the accompanying conclusion. It has been featured that the monetary sponsorship of the construction business assumes a vital part in all parts of the development process and that the construction industry is straightforwardly influenced by monetary emergencies, whether they happen locally or around the world. To work on the adequacy of funding of ventures abandoned in Iraq during seasons of monetary emergency, associations that are exceptionally useful to project construction and implementation were taken on. These organizations likewise upheld the utilization of venture as a substitute option and undertaking renovation. Using AHP is great for deciding the Best Association Contract, which improves the monetary exhibition of the structure all through its life. The result shows that the BOT contract is the most ideal option for this venture and has a superior score of 0.261. The sending of the Organizations methods all through the undertaking's structure stage is one of this study's deficiencies. To pick the best money system for associations in building projects, utilize different philosophies and contextual analyses in future examination.

REFERENCES:

1. Manupati, V. K., Ramkumar, M., & Samanta, D. (2018). A multi-criteria decision making approach for the urban renewal in Southern India. Sustainable Cities and Society, 42, 471-481.

2. Erdogan, S. A., Saparauskas, J., & Turskis, Z. (2019). A multi-criteria decision-making model to choose the best option for sustainable construction management. Sustainability, 11(8), 2239.

3. Jena, R., Pradhan, B., & Beydoun, G. (2020). Earthquake vulnerability assessment in Northern Sumatra province by using a multi-criteria decision-making model. International journal of disaster risk reduction, 46, 101518.

4. Abdullah, A. K., & Alshibani, A. (2022). Multi-criteria decision-making framework for selecting sustainable private partners for housing projects. Journal of Financial Management of Property and Construction, 27(1), 112-140.

5. Bivina, G. R., & Parida, M. (2020). Prioritizing pedestrian needs using a multi-criteria decision approach for a sustainable built environment in the Indian context. Environment, Development and Sustainability, 22, 4929-4950.

6. Nguyen, L. C., & Notteboom, T. (2016). A multi-criteria approach to dry port location in developing economies with application to Vietnam. The Asian Journal of Shipping and Logistics, 32(1), 23-32.

7. Askarifar, K., Motaffef, Z., & Aazaami, S. (2018). An investment development framework in Iran's seashores using TOPSIS and best-worst multi-criteria decision making methods. Decision Science Letters, 7(1), 55-64.

8. Amorocho-Daza, H., Cabrales, S., Santos, R., & Saldarriaga, J. (2019). A new multi-Criteria decision analysis methodology for the selection of new water supply infrastructure. Water, 11(4), 805.

9. Yap, E. H., Tan, H. C., & Chia, F. C. 2010. Causes of abandoned construction projects. This page is intentionally left blank.

10. Cheung, E., Chan, A. P., & Kajewski, S. 2009. Enhancing value for money in public private partnership projects. Journal of Financial Management of Property and Construction.

11. Ministry of Planning, Baghdad, Iraq Budget execution report, (2019).

iНе можете найти то, что вам нужно? Попробуйте сервис подбора литературы.

12. Bohun, V. 2001. Developing Best Practices for Promoting Private Sector Investment in Infrastructure: Roads

13. Cheng, Z., Wang, H., Xiong, W., Zhu, D., & Cheng, L. 2020. Public-private partnership as a driver of sustainable development: toward a conceptual framework of sustainability-oriented PPP. Environment, Development and Sustainability, 1-21.

14. Anopchenko, T., Gorbaneva, O., Lazareva, E., Murzin, A., & Ougolnitsky, G. 2019. Modeling Public—Private Partnerships in Innovative Economy: A Regional Aspect. Sustainability, 11(20), 5588

15. Noorzai, E., Jafari, K. G., Heshmatnezhad, R., & Vahedi, B. 2016. Implementing AHP approach to select an appropriate financing method for PPP highway projects in Iran. International Journal of Structural and Civil Engineering Research, 3(1), 67-73

16. Bashiri, M., Ebrahimi, S., Fazlali, M., Hosseini, S. J., Jamal, N., & Salehvand, P. 2011. Analytical comparison between BOT, BOOT, and PPP project delivery systems. In 6th International Project Management Conference. At Tehran: Iran.

17. Confoy, B., Love, P. E. D., Wood, B. M., & Picken, D. H. 1999. Build-own-operate: the procurement of correctional services. Profitable Partnering in Construction Procurement, 461-473.

18. Confoy, B., Love, P. E. D., Wood, B. M., & Picken, D. H. 1999. Build-own-operate: the procurement of correctional services. Profitable Partnering in Construction Procurement, 461-473.

19. Saaty, T. L. 2008. Decision making with the analytic hierarchy process. International journal of services sciences, 1(1), 83-98.

20. Darko, A., Chan, A. P. C., Ameyaw, E. E., Owusu, E. K., Parn, E., & Edwards, D. J. 2019. Review of application of analytic hierarchy process (AHP) in construction. International Journal of Construction Management, 19(5), 436-452.